Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
19 Jul 2023 | 10000m Pipe laid | Koothuparamba Proj AE 2 | |
14 Jul 2023 | 9750m Pipe laid | Koothuparamba Proj AE 2 | |
05 Jul 2023 | Pipe supplying on progress and 9500m Pipe laid | Koothuparamba Proj AE 2 | |
30 Jun 2023 | Pipe supplying on progress and 9000m Pipe laid | Koothuparamba Proj AE 2 | |
23 Jun 2023 | 4700m Pipe laid | Koothuparamba Proj AE 2 | |
19 Jun 2023 | 4500m Pipe laid, | Koothuparamba Proj AE 2 | |
12 Jun 2023 | 4200m Pipe laid, First and part bill submitted | Koothuparamba Proj AE 2 | |
06 Jun 2023 | 3000m Pipe laid, First and part bill submitted | Koothuparamba Proj AE 2 | |
01 Jun 2023 | Pipe supplying on progress ,2000m Pipe laid, First and part bill submitted | Koothuparamba Proj AE 2 | |
29 May 2023 | Pipe supplying and Laying started | Koothuparamba Proj AE 2 |