| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 23 Jun 2023 | 4700m Pipe laid | Koothuparamba Proj AE 2 | |
| 19 Jun 2023 | 4500m Pipe laid, | Koothuparamba Proj AE 2 | |
| 12 Jun 2023 | 4200m Pipe laid, First and part bill submitted | Koothuparamba Proj AE 2 | |
| 06 Jun 2023 | 3000m Pipe laid, First and part bill submitted | Koothuparamba Proj AE 2 | |
| 01 Jun 2023 | Pipe supplying on progress ,2000m Pipe laid, First and part bill submitted | Koothuparamba Proj AE 2 | |
| 29 May 2023 | Pipe supplying and Laying started | Koothuparamba Proj AE 2 | |
| 27 May 2023 | Pipe supplied | Koothuparamba Proj AE 2 |