| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 05 Sep 2023 | 23780 m pipe laid | Koothuparamba Proj AE 2 | |
| 24 Aug 2023 | 21786m pipe laid | Koothuparamba Proj AE 2 | |
| 16 Aug 2023 | 20786 m pipe laid. | Koothuparamba Proj AE 2 | |
| 10 Aug 2023 | 20000m Pipe laid. | Koothuparamba Proj AE 2 | |
| 03 Aug 2023 | 15000m Pipe laid. Due to heavy rain work is slow in progress | Koothuparamba Proj AE 2 | |
| 26 Jul 2023 | 10000 m Pipe laid. Due to heavy rain work is slow in progress | Koothuparamba Proj AE 2 | |
| 19 Jul 2023 | 10000m Pipe laid | Koothuparamba Proj AE 2 | |
| 14 Jul 2023 | 9750m Pipe laid | Koothuparamba Proj AE 2 | |
| 05 Jul 2023 | Pipe supplying on progress and 9500m Pipe laid | Koothuparamba Proj AE 2 | |