Overall Project Status

Status Date Overall Project Status Project Officer Contact
13 May 2024 95665m pipe laid . 995 HTC given Koothuparamba Proj AE 2
09 May 2024 90350m pipe laid . 995 HTC given Koothuparamba Proj AE 2
06 May 2024 89920m pipe laid . 995 HTC given Koothuparamba Proj AE 2
02 May 2024 88514m pipe laid . 995 HTC given Koothuparamba Proj AE 2
30 Apr 2024 82125m pipe laid . 995 HTC given Koothuparamba Proj AE 2
25 Apr 2024 80710 m pipe laid . 995 HTC given Koothuparamba Proj AE 2
22 Apr 2024 78590 m pipe laid . 995 HTC given Koothuparamba Proj AE 2
18 Apr 2024 75985m pipe laid . 995 HTC given Koothuparamba Proj AE 2
15 Apr 2024 75715m pipe laid . 995 HTC given Koothuparamba Proj AE 2
11 Apr 2024 75620m pipe laid . 995 HTC given Koothuparamba Proj AE 2