Project | KIIFB-Chathannoor drinking water project |
---|---|
Project Code | KLMKIIFB0918466 |
Type | Main project |
Funding Agency | KIIFB |
Category | KIIFB |
Type of scheme | Water Supply |
Scheme | KIIFB |
Description | KIIFB-Chathannoor drinking water project |
Status | Completed |
District | Kollam |
Executing Office | Kollam Project Dn |
AS Amount (Rs) | 600000000 |
AS Number | KWA/P1-/10352017-18-part XI |
TS Amount (Rs) | 315393000 |
TS Number | 363/2018 |
Total Bill Submitted (Rs) | 149332027 |
Total Bill Paid (Rs) | 141658188 |
Population Benefitted | 188819 |
Capacity in MLD | 19.00 |
Actual Project Completion Date | 30 Jun 2022 |
Coverage | 188819 |
Implementation Schedule | Download |
Work Plan | Download |
No. | Project Name | Location | View |
---|---|---|---|
1 | PACKAGE 1-Extension of Distribution system from JICA Scheme in various villages under Chathannoor Constituency-Paravoor Municipality | Kollam Project Dn | |
2 | PACKAGE II-Extension of Distribution system from JICA Scheme in various villages under Chathannoor Constituency-Pooyappally village | Kollam Project Dn | |
3 | PACKAGE III-Extension of Distribution system from JICA Scheme in various villages under Chathannoor Constituency-Meenad village | Kollam Project Dn | |
4 | PACKAGE IV-KIIFB-Extension of Distribution system from JICA Scheme in various villages under Chathannoor Constituency-Chirakkara village | Kollam Project Dn | |
5 | PACKAGE V-Extension of Distribution system from JICA Scheme in various villages under Chathannoor Constituency-Paravoor. | Kollam Project Dn | |
6 | PACKAGEVI-Extension of Distribution system from JICA Scheme in various villages under Chathannoor Constituency-Poothakkulam | Kollam Project Dn | |
7 | PACKAGE VII-Extension of Distribution system from JICA Scheme in various villages under Chathannoor Constituency-Adichanalloor | Kollam Project Dn |
Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
01 Jan 2023 | All packages completed. | Kollam Project HD | |
01 Aug 2022 | Out of 7 packages, 5 Packages completed. Adichanaloor (85 % completed) and Poothakulam (72% completed) . The scheme is expected to be completed by 31/08/2022 | Kollam Project HD | |
18 Apr 2022 | Out of 7 packages, 5 Packages were completed. Adichanaloor (58 % completed) and Poothakulam (63% completed) packages progressing. The scheme is expected to be completed by 30/06/2022. | Kollam Project HD | |
18 Apr 2022 | Out of 7 packages, 4 Packages were completed. Adichanaloor, Paravoor Municipality and Poothakulam packages progressing. The scheme is expected to be completed by 30/06/2022. | Kollam Project HD | |
01 Feb 2022 | Out of 7 packages, 4 Packages were completed. Adichanaloor, Paravoor Municipality and Poothakulam packages progressing. The scheme is expected to be completed by 31/03/2022. The overall progress is 81.43 % | Kollam Project HD |
Date of start of Project | 16/12/2019 |
---|---|
Scheduled date of Completion of the Project | 31 Mar 2022 |
Expected date of Completion | 31/08/2022 |
AS Date | 05 Apr 2019 |
---|---|
TS Date | 14 Aug 2019 |
Project Officers | View |
---|