KIIFB-Chathannoor drinking water project

Project KIIFB-Chathannoor drinking water project
Project Code KLMKIIFB0918466
Type Main project
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description KIIFB-Chathannoor drinking water project
Status Completed
District Kollam
Executing Office Kollam Project Dn
AS Amount (Rs) 600000000
AS Number KWA/P1-/10352017-18-part XI
TS Amount (Rs) 315393000
TS Number 363/2018
Total Bill Submitted (Rs) 149332027
Total Bill Paid (Rs) 141658188
Population Benefitted 188819
Capacity in MLD 19.00
Actual Project Completion Date 30 Jun 2022
Coverage 188819
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 PACKAGE 1-Extension of Distribution system from JICA Scheme in various villages under Chathannoor Constituency-Paravoor Municipality Kollam Project Dn
2 PACKAGE II-Extension of Distribution system from JICA Scheme in various villages under Chathannoor Constituency-Pooyappally village Kollam Project Dn
3 PACKAGE III-Extension of Distribution system from JICA Scheme in various villages under Chathannoor Constituency-Meenad village Kollam Project Dn
4 PACKAGE IV-KIIFB-Extension of Distribution system from JICA Scheme in various villages under Chathannoor Constituency-Chirakkara village Kollam Project Dn
5 PACKAGE V-Extension of Distribution system from JICA Scheme in various villages under Chathannoor Constituency-Paravoor. Kollam Project Dn
6 PACKAGEVI-Extension of Distribution system from JICA Scheme in various villages under Chathannoor Constituency-Poothakkulam Kollam Project Dn
7 PACKAGE VII-Extension of Distribution system from JICA Scheme in various villages under Chathannoor Constituency-Adichanalloor Kollam Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
01 Jan 2023 All packages completed. Kollam Project HD
01 Aug 2022 Out of 7 packages, 5 Packages completed. Adichanaloor (85 % completed) and Poothakulam (72% completed) . The scheme is expected to be completed by 31/08/2022 Kollam Project HD
18 Apr 2022 Out of 7 packages, 5 Packages were completed. Adichanaloor (58 % completed) and Poothakulam (63% completed) packages progressing. The scheme is expected to be completed by 30/06/2022. Kollam Project HD
18 Apr 2022 Out of 7 packages, 4 Packages were completed. Adichanaloor, Paravoor Municipality and Poothakulam packages progressing. The scheme is expected to be completed by 30/06/2022. Kollam Project HD
01 Feb 2022 Out of 7 packages, 4 Packages were completed. Adichanaloor, Paravoor Municipality and Poothakulam packages progressing. The scheme is expected to be completed by 31/03/2022. The overall progress is 81.43 % Kollam Project HD

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 16/12/2019
Scheduled date of Completion of the Project 31 Mar 2022
Expected date of Completion 31/08/2022

Processing Dates

AS Date 05 Apr 2019
TS Date 14 Aug 2019

Other details