Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
01 Jan 2023 | All packages completed. | Kollam Project HD | |
01 Aug 2022 | Out of 7 packages, 5 Packages completed. Adichanaloor (85 % completed) and Poothakulam (72% completed) . The scheme is expected to be completed by 31/08/2022 | Kollam Project HD | |
18 Apr 2022 | Out of 7 packages, 5 Packages were completed. Adichanaloor (58 % completed) and Poothakulam (63% completed) packages progressing. The scheme is expected to be completed by 30/06/2022. | Kollam Project HD | |
18 Apr 2022 | Out of 7 packages, 4 Packages were completed. Adichanaloor, Paravoor Municipality and Poothakulam packages progressing. The scheme is expected to be completed by 30/06/2022. | Kollam Project HD | |
01 Feb 2022 | Out of 7 packages, 4 Packages were completed. Adichanaloor, Paravoor Municipality and Poothakulam packages progressing. The scheme is expected to be completed by 31/03/2022. The overall progress is 81.43 % | Kollam Project HD | |
01 Feb 2022 | Out of 7 packages, 4 Packages were completed. Adichanaloor, Paravoor Municipality and Poothakulam packages progressing. The scheme is expected to be completed by 31/03/2022 | Kollam Project HD | |
13 Jan 2022 | Out of 7 packages, 4 Packages were completed. Adichanaloor and Paravoor Municipality packages ongoing and balance pipe supply order placed by the contractor and restarted by 27.12.21. | Kollam Project HD | |
20 Dec 2021 | Out of 7 packages 4 Packages completed...Adichanaloor and Paravoor Muncipality packages ongoing and balance pipe supply order placed by contractor and scheduled to restrart works by 27.12.21 | Kollam Project HD | |
02 Nov 2021 | Out of 7 packages 4 works completed...adichanaloor package ongoing and No work restarted and not supplied balance pipe and for POOTHAKULAM and for paravoor municipality.. requested time extension granted upto 31.12.2021 | Kollam Project HD | |
27 Oct 2021 | Out of 7 packages 4 works completed...adichanaloor package ongoing and No work restarted and not supplied balance pipe and notice issued for termination and for arranging works risk and cost for POOTHAKULAM and for paravoor municipality.. requested time extension granted upto 31.12.2021 | Kollam Project HD |