| Project | PACKAGE III-Extension of Distribution system from JICA Scheme in various villages under Chathannoor Constituency-Meenad village |
|---|---|
| Project Code | KLMGOK0918466P3 |
| Type | Package |
| Main Project | KIIFB-Chathannoor drinking water project |
| Funding Agency | KIIFB |
| Category | KIIFB | Type of scheme | Water Supply |
| Description | PACKAGE III-Extension of Distribution system from JICA Scheme in various villages under Chathannoor Constituency-Meenad village |
| Status | On-going |
| District | Kollam |
| Executing Office | Kollam Project Dn |
| TS Amount (Rs) | 27140000 |
| TS Number | 244/2018 |
| Technical specification | Extension of Distribution system from JICA Scheme in various villages under Chathannoor Constituency-Meenad village |
Project Progress Status |
Project Progress Status |
| Date of start of Package | 17/12/2019 |
|---|---|
| Scheduled date of Completion as per agreement | 16 Sep 2020 |
| Expected date of Completion | 28/02/2021 |
| TS Date | 14 Aug 2019 |
|---|---|
| Estimate Approval | 14 Aug 2018 |
| Tender Closing | 27 Sep 2019 |
| Price bid opening | 27 Sep 2019 |
| Workorder Date | 20 Nov 2019 |
|---|---|
| Agreement Date | 17 Dec 2019 |
| Kollam Project Dn EE |
| Date: 02/03/2021 |
Work has been completed | 100% Completed
Works completed..
| Kollam Project Dn EE |
| Date: 27/02/2021 |
Work in progress | 96% Completed
laying works completed, Interconnection and road restoration works in progress.