Project | PACKAGE III-Extension of Distribution system from JICA Scheme in various villages under Chathannoor Constituency-Meenad village |
---|---|
Project Code | KLMGOK0918466P3 |
Type | Package |
Main Project | KIIFB-Chathannoor drinking water project |
Funding Agency | KIIFB |
Category | KIIFB |
Type of scheme | Water Supply |
Scheme | KIIFB |
Description | PACKAGE III-Extension of Distribution system from JICA Scheme in various villages under Chathannoor Constituency-Meenad village |
Status | On-going |
District | Kollam |
Executing Office | Kollam Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 27140000 |
TS Number | 244/2018 |
Technical specification | Extension of Distribution system from JICA Scheme in various villages under Chathannoor Constituency-Meenad village |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 17/12/2019 |
---|---|
Scheduled date of Completion as per agreement | 16 Sep 2020 |
Expected date of Completion | 28/02/2021 |
TS Date | 14 Aug 2019 |
---|---|
Estimate Approval | 14 Aug 2018 |
Tender Closing | 27 Sep 2019 |
Price bid opening | 27 Sep 2019 |
Workorder Date | 20 Nov 2019 |
---|---|
NA | 17 Dec 2019 |
Kollam Project HD |
Date: 02/03/2021 |
Work has been completed | 100% Completed
Works completed..
Kollam Project HD |
Date: 27/02/2021 |
Work in progress | 96% Completed
laying works completed, Interconnection and road restoration works in progress.