Project | PACKAGE VII-Extension of Distribution system from JICA Scheme in various villages under Chathannoor Constituency-Adichanalloor |
---|---|
Project Code | KLMGOK0918466P7 |
Type | Package |
Main Project | KIIFB-Chathannoor drinking water project |
Funding Agency | KIIFB |
Category | KIIFB |
Type of scheme | Water Supply |
Scheme | KIIFB |
Description | PACKAGE VII-Extension of Distribution system from JICA Scheme in various villages under Chathannoor Constituency-Adichanalloor |
Status | On-going |
District | Kollam |
Executing Office | Kollam Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 107029188 |
TS Number | 2944 |
Technical specification | Line extension from JICA |
Contractor | S Raju (Mob: 9447206743) |
Issue date | Solved On | Action Taken On | Category | Description | Comments | Issue Status |
---|---|---|---|---|---|---|
24 Oct 2021 | Pending | Pending | Road Cut Related Risk | Project ID #3182 created and issue id # 8035 addressed in PMG | No comments available. | Pending |
10 Feb 2021 | Pending | Pending | Road Cut Related Risk | NHAI sanction pending for laying between Kottiyam and ithikkara bridge.(Both sides) | No comments available. | Pending |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 06/05/2020 |
---|---|
Scheduled date of Completion as per agreement | 31 Jul 2022 |
Expected date of Completion | 31/07/2022 |
TS Date | 17 Aug 2019 |
---|---|
Estimate Approval | 17 Aug 2019 |
NIT Approval | 17 Aug 2019 |
Tender Closing | 12 Feb 2020 |
Technichal Pre-Qualification | 12 Feb 2020 |
Price bid opening | 14 Feb 2020 |
Workorder Date | 10 Mar 2020 |
---|---|
NA | 06 May 2020 |
Kollam Project HD |
Date: 20/08/2022 |
Work has been completed | 100% Completed
Work completed..
Kollam Project HD |
Date: 10/08/2022 |
Work in progress | 85% Completed
Laying works in PWD road in progress- Pipe laying 85% completed. .Road restoration works in panchayath roads in progress.works nearing completion..