PACKAGE VII-Extension of Distribution system from JICA Scheme in various villages under Chathannoor Constituency-Adichanalloor

Project PACKAGE VII-Extension of Distribution system from JICA Scheme in various villages under Chathannoor Constituency-Adichanalloor
Project Code KLMGOK0918466P7
Type Package
Main Project KIIFB-Chathannoor drinking water project
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Description PACKAGE VII-Extension of Distribution system from JICA Scheme in various villages under Chathannoor Constituency-Adichanalloor
Status On-going
District Kollam
Executing Office Kollam Project Dn
TS Amount (Rs) 107029188
TS Number 2944
Technical specification Line extension from JICA

No project review have been added to this project

Project Progress Status

Project Progress Status

Duration & Sanction dates

Date of start of Package 06/05/2020
Scheduled date of Completion as per agreement 05 Nov 2021
Expected date of Completion 05/11/2021

Processing Dates

TS Date 17 Aug 2019
Estimate Approval 17 Aug 2019
NIT Approval 17 Aug 2019
Tender Closing 12 Feb 2020
Price bid opening 14 Feb 2020

Approval Dates

Workorder Date 10 Mar 2020
Agreement Date 06 May 2020

Other details

Project Schedule View
Project Components View
Project Officers View

Location

Project Status Updations See All Status Updations

Kollam Project Dn EE
Date: 14/06/2021

Work in progress | 14% Completed

10.4km laid out of 70 kms , PWD road restoration completed in one stretch,Valve cambers works in progress. Laing works stopped temporarily due to lock down restrictions in Adichanaloor Panchayath..

Kollam Project Dn EE
Date: 08/06/2021

Work in progress | 13% Completed

Work stopped due to lock down restrictions.