| Project | PACKAGE VII-Extension of Distribution system from JICA Scheme in various villages under Chathannoor Constituency-Adichanalloor |
|---|---|
| Project Code | KLMGOK0918466P7 |
| Type | Package |
| Main Project | KIIFB-Chathannoor drinking water project |
| Funding Agency | KIIFB |
| Category | KIIFB | Type of scheme | Water Supply |
| Description | PACKAGE VII-Extension of Distribution system from JICA Scheme in various villages under Chathannoor Constituency-Adichanalloor |
| Status | On-going |
| District | Kollam |
| Executing Office | Kollam Project Dn |
| TS Amount (Rs) | 107029188 |
| TS Number | 2944 |
| Technical specification | Line extension from JICA |
Project Progress Status |
Project Progress Status |
| Date of start of Package | 06/05/2020 |
|---|---|
| Scheduled date of Completion as per agreement | 05 Nov 2021 |
| Expected date of Completion | 05/11/2021 |
| TS Date | 17 Aug 2019 |
|---|---|
| Estimate Approval | 17 Aug 2019 |
| NIT Approval | 17 Aug 2019 |
| Tender Closing | 12 Feb 2020 |
| Price bid opening | 14 Feb 2020 |
| Workorder Date | 10 Mar 2020 |
|---|---|
| Agreement Date | 06 May 2020 |
| Kollam Project Dn EE |
| Date: 14/06/2021 |
Work in progress | 14% Completed
10.4km laid out of 70 kms , PWD road restoration completed in one stretch,Valve cambers works in progress. Laing works stopped temporarily due to lock down restrictions in Adichanaloor Panchayath..
| Kollam Project Dn EE |
| Date: 08/06/2021 |
Work in progress | 13% Completed
Work stopped due to lock down restrictions.