Project | PACKAGE 1-Extension of Distribution system from JICA Scheme in various villages under Chathannoor Constituency-Paravoor Municipality |
---|---|
Project Code | KLMGOK0918466P1 |
Type | Package |
Main Project | KIIFB-Chathannoor drinking water project |
Funding Agency | KIIFB |
Category | KIIFB |
Type of scheme | Water Supply |
Scheme | KIIFB |
Description | PACKAGE 1-Extension of Distribution system from JICA Scheme in various villages under Chathannoor Constituency-Paravoor Municipality |
Status | On-going |
District | Kollam |
Executing Office | Kollam Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 18344000 |
TS Number | 240/2018 |
Technical specification | laying of 160mm & 110mm 6kg/cm2 in various nodes in paravoor municipaliy. 1.160mm 6Kg PVC-1250M 2.110mm 6Kg PVC-16116M 3. 100mm GI Pipe-253M 4. 150mm GI Pipe-50M Total 17.36KM PVC & 303M GI |
Contractor | ADARSH ENGINEERS (Mob: 9447197547) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 28/05/2020 |
---|---|
Scheduled date of Completion as per agreement | 28 Feb 2022 |
Expected date of Completion | 28/02/2022 |
TS Date | 14 Aug 2019 |
---|---|
Estimate Approval | 14 Aug 2020 |
Tender Closing | 05 Feb 2020 |
Price bid opening | 07 Feb 2020 |
Workorder Date | 27 Apr 2020 |
---|---|
NA | 28 May 2020 |
Kollam Project HD |
Date: 30/04/2022 |
Work has been completed | 100% Completed
C C 2 and part bill submitted.
Kollam Project HD |
Date: 29/04/2022 |
Work has been completed | 100% Completed
C C 2 and part bill submitted.