| Project | PACKAGE 1-Extension of Distribution system from JICA Scheme in various villages under Chathannoor Constituency-Paravoor Municipality |
|---|---|
| Project Code | KLMGOK0918466P1 |
| Type | Package |
| Main Project | KIIFB-Chathannoor drinking water project |
| Funding Agency | KIIFB |
| Category | KIIFB | Type of scheme | Water Supply |
| Description | PACKAGE 1-Extension of Distribution system from JICA Scheme in various villages under Chathannoor Constituency-Paravoor Municipality |
| Status | On-going |
| District | Kollam |
| Executing Office | Kollam Project Dn |
| TS Amount (Rs) | 18344000 |
| TS Number | 240/2018 |
| Technical specification | laying of 160mm & 110mm 6kg/cm2 in various nodes in paravoor municipaliy. 1.160mm 6Kg PVC-1250M 2.110mm 6Kg PVC-16116M 3. 100mm GI Pipe-253M 4. 150mm GI Pipe-50M Total 17.36KM PVC & 303M GI |
Project Progress Status |
Project Progress Status |
| Date of start of Package | 28/05/2020 |
|---|---|
| Scheduled date of Completion as per agreement | 30 Sep 2021 |
| Expected date of Completion | 31/05/2021 |
| TS Date | 14 Aug 2019 |
|---|---|
| Estimate Approval | 14 Aug 2020 |
| Tender Closing | 05 Feb 2020 |
| Price bid opening | 07 Feb 2020 |
| Workorder Date | 27 Apr 2020 |
|---|---|
| Agreement Date | 28 May 2020 |
| Kollam Project Dn EE |
| Date: 13/06/2021 |
Work in progress | 46% Completed
Work in progress | 46% Completed | No work dueto lock down.
| Kollam Project Dn EE |
| Date: 12/06/2021 |
Work in progress | 46% Completed
No work dueto lock down.