Project | PACKAGEVI-Extension of Distribution system from JICA Scheme in various villages under Chathannoor Constituency-Poothakkulam |
---|---|
Project Code | KLMGOK0918466P6 |
Type | Package |
Main Project | KIIFB-Chathannoor drinking water project |
Funding Agency | KIIFB |
Category | KIIFB |
Type of scheme | Water Supply |
Scheme | KIIFB |
Description | PACKAGEVI-Extension of Distribution system from JICA Scheme in various villages under Chathannoor Constituency-Poothakkulam |
Status | On-going |
District | Kollam |
Executing Office | Kollam Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 23045800 |
TS Number | 2896/2019-20 |
Technical specification | laying of pipe sizes from 75mm to 140mm pvc lines from JICA lines 1.140mm 6Kg PVC-1805M 2.110mm 6Kg PVC-3478M 3.90mm 6Kg PVC-8594M 4.90mm 8Kg PVC-2484M 5.75mm 6Kg PVC-14902M 6.75mm 8Kg PVC-1848M 7.125mm GI Pipe-20M 8.110mm GI Pipe-40M 9.80mm GI Pipe-110M 10.65mm GI Pipe-70M total - 33.11KM PVC & 240M GI |
Contractor | M.V. RAJEEV (Mob: 9400336494) |
Review Date | Review Message | Review Attended By |
---|---|---|
18 Dec 2021 | Date completions are to be updated urgently | AEE,AE |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 28/05/2020 |
---|---|
Scheduled date of Completion as per agreement | 30 Apr 2022 |
Expected date of Completion | 31/08/2022 |
TS Date | 14 Aug 2019 |
---|---|
Estimate Approval | 14 Aug 2019 |
NIT Approval | 13 Jan 2020 |
Tender Closing | 05 Feb 2020 |
Technichal Pre-Qualification | 10 Feb 2020 |
Price bid opening | 13 Feb 2020 |
Workorder Date | 22 Apr 2020 |
---|---|
NA | 28 May 2021 |
Kollam Project HD |
Date: 14/09/2022 |
Work has been completed | 100% Completed
Trail running in progress .
Kollam Project HD |
Date: 03/09/2022 |
Work has been completed | 100% Completed
Trail running in progress .