PACKAGEVI-Extension of Distribution system from JICA Scheme in various villages under Chathannoor Constituency-Poothakkulam

Project PACKAGEVI-Extension of Distribution system from JICA Scheme in various villages under Chathannoor Constituency-Poothakkulam
Project Code KLMGOK0918466P6
Type Package
Main Project KIIFB-Chathannoor drinking water project
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description PACKAGEVI-Extension of Distribution system from JICA Scheme in various villages under Chathannoor Constituency-Poothakkulam
Status On-going
District Kollam
Executing Office Kollam Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 23045800
TS Number 2896/2019-20
Technical specification laying of pipe sizes from 75mm to 140mm pvc lines from JICA lines 1.140mm 6Kg PVC-1805M 2.110mm 6Kg PVC-3478M 3.90mm 6Kg PVC-8594M 4.90mm 8Kg PVC-2484M 5.75mm 6Kg PVC-14902M 6.75mm 8Kg PVC-1848M 7.125mm GI Pipe-20M 8.110mm GI Pipe-40M 9.80mm GI Pipe-110M 10.65mm GI Pipe-70M total - 33.11KM PVC & 240M GI
Contractor M.V. RAJEEV (Mob: 9400336494)

Project Review

See All Review messages
Review Date Review Message Review Attended By
18 Dec 2021 Date completions are to be updated urgently AEE,AE

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 28/05/2020
Scheduled date of Completion as per agreement 30 Apr 2022
Expected date of Completion 31/08/2022

Processing Dates

TS Date 14 Aug 2019
Estimate Approval 14 Aug 2019
NIT Approval 13 Jan 2020
Tender Closing 05 Feb 2020
Technichal Pre-Qualification 10 Feb 2020
Price bid opening 13 Feb 2020

Approval Dates

Workorder Date 22 Apr 2020
NA 28 May 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kollam Project HD
Date: 14/09/2022

Work has been completed | 100% Completed

Trail running in progress .

Kollam Project HD
Date: 03/09/2022

Work has been completed | 100% Completed

Trail running in progress .