| Project | PACKAGE IV-KIIFB-Extension of Distribution system from JICA Scheme in various villages under Chathannoor Constituency-Chirakkara village |
|---|---|
| Project Code | KLMGOK0918466P4 |
| Type | Package |
| Main Project | KIIFB-Chathannoor drinking water project |
| Funding Agency | KIIFB |
| Category | KIIFB | Type of scheme | Water Supply |
| Description | PACKAGE IV-Extension of Distribution system from JICA Scheme in various villages under Chathannoor Constituency-Chirakkara village |
| Status | On-going |
| District | Kollam |
| Executing Office | Kollam Project Dn |
| TS Amount (Rs) | 47940000 |
| TS Number | 265/2018 |
| Technical specification | Line extension from existing JICA scheme |
Project Progress Status |
Project Progress Status |
| Date of start of Package | 16/12/2019 |
|---|---|
| Scheduled date of Completion as per agreement | 15 Dec 2020 |
| Expected date of Completion | 15/02/2021 |
| TS Date | 14 Aug 2019 |
|---|---|
| Estimate Approval | 14 Aug 2019 |
| Tender Closing | 23 Sep 2020 |
| Price bid opening | 25 Sep 2020 |
| Workorder Date | 20 Nov 2019 |
|---|---|
| Agreement Date | 06 Dec 2019 |
| Kollam Project Dn EE |
| Date: 02/03/2021 |
Work has been completed | 100% Completed
laying works completed..
| Kollam Project Dn EE |
| Date: 26/02/2021 |
Work in progress | 96% Completed
33.245km laid out of 34.669 km, hydro testing, interconnection works and road restoration works in progress.