PACKAGE IV-KIIFB-Extension of Distribution system from JICA Scheme in various villages under Chathannoor Constituency-Chirakkara village

Project PACKAGE IV-KIIFB-Extension of Distribution system from JICA Scheme in various villages under Chathannoor Constituency-Chirakkara village
Project Code KLMGOK0918466P4
Type Package
Main Project KIIFB-Chathannoor drinking water project
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description PACKAGE IV-Extension of Distribution system from JICA Scheme in various villages under Chathannoor Constituency-Chirakkara village
Status On-going
District Kollam
Executing Office Kollam Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 47940000
TS Number 265/2018
Technical specification Line extension from existing JICA scheme

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 16/12/2019
Scheduled date of Completion as per agreement 15 Dec 2020
Expected date of Completion 15/02/2021

Processing Dates

TS Date 14 Aug 2019
Estimate Approval 14 Aug 2019
Tender Closing 23 Sep 2020
Price bid opening 25 Sep 2020

Approval Dates

Workorder Date 20 Nov 2019
NA 06 Dec 2019

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kollam Project HD
Date: 02/03/2021

Work has been completed | 100% Completed

laying works completed..

Kollam Project HD
Date: 26/02/2021

Work in progress | 96% Completed

33.245km laid out of 34.669 km, hydro testing, interconnection works and road restoration works in progress.