Supplying, laying, Commissioning and maintaining 1016mm dia.8.8mm thick M.S Clear Water pumping main from TP to OHBR at Manichithode, 914mm M .S CWGM form Manichithode to Anandavalleswaram and Construction of 54LL OHSR at Manichithode
Project |
Supplying, laying, Commissioning and maintaining 1016mm dia.8.8mm thick M.S Clear Water pumping main from TP to OHBR at Manichithode, 914mm M .S CWGM form Manichithode to Anandavalleswaram and Construction of 54LL OHSR at Manichithode |
Project Code |
KLMGOK0117465P3 |
Type |
Package |
Main Project |
PROJECTS UNDER KERALA INFRA.INVT. FUND BOARD KIIFB(74)-Augmentation of WSS to Kollam Corporation Phase II(7503)
|
Funding Agency |
KIIFB |
Category |
KIIFB |
Type of scheme |
Water Supply |
Scheme |
KIIFB |
Description |
Supplying, laying, Commissioning and maintaining 1016mm dia.8.8mm thick M.S Clear Water pumping main from TP to OHSR at Manichithode, 914mm M .S CWGM form Manichithode to Anandavalleswaram and Construction of 54LL OHSR at Manichithode - TS Amount 2350000000(235 cr) |
Status |
On-going |
District |
Kollam |
Executing Office |
Kollam Project Dn |
Agreement Number |
|
Agreement Date |
|
TS Amount (Rs) |
476169000 |
TS Number |
KWA/CE(SR)/18-2016-17 dtd 23/01/2017 |
Technical specification |
Supplying, laying, Commissioning and maintaining 1016mm dia.8.8mm thick M.S Clear Water pumping main - 3835 metre , 914mm M .S CWGM 6130 meter and Construction of 54LL OHSR |
Contractor |
M/S Shree Contractor (Mob: 9829855082) |
No project review have been added to this project
Reported Issues
Issue date |
Solved On |
Action Taken On |
Category |
Description |
Comments |
Issue Status |
26 Oct 2022 |
Pending |
Pending |
Approval/Permissions Related (from other departments excluding road cut permission and land related) |
Kallupalam bridge pipe rack for laying 914mm MS pipe |
Issue solved and pipe rack erected and pipe laying work completed at Kallupalam on 28.12.2022 |
Action Taken |
23 Aug 2022 |
Pending |
Pending |
Approval/Permissions Related (from other departments excluding road cut permission and land related) |
ഞാങ്കടവ് കുടിവെള്ള പദ്ധതിക്ക് വേണ്ടി പൈപ്പ് ലൈൻ സ്ഥാപിക്കുന്നതിനുവേണ്ടി റോഡ് കട്ട് ചെയ്യുന്നത് സംബന്ധിച്ച്
|
Issue solved |
Action Taken |
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
Date of start of Package |
30/08/2019 |
Scheduled date of Completion as per agreement |
28 Feb 2021 |
Expected date of Completion |
31/03/2023 |
Processing Dates
TS Date |
22 Jan 2018 |
Estimate Approval |
22 Jan 2018 |
NIT Approval |
22 Mar 2018 |
Tender Closing |
17 Dec 2018 |
Technichal Pre-Qualification |
26 Feb 2019 |
Price bid opening |
26 Feb 2019 |
Approval Dates
Workorder Date |
24 Jun 2019 |
NA |
30 Aug 2019 |
Other details
Project Schedule |
View |
Project Components |
View |
Project Officers |
View |
Kollam Project Dn EE |
Date: 30/03/2023 |
Work has been completed | 100% Completed
914 mm gravity main – 5714.38 m laid out of 6130m,1016 mm clear water pumping main - 3716.31m laid out of 3835m. Hydro testing of pipelines - 914 mm- 5341.5m completed, 1016mm - 3562m completed. Valve chamber works- 10 Nos completed 6 Nos balance. Cathodic protection work in progress. The whole plastering work of 54LL OHSR at Manichithodu was completed and the Painting work was completed. The casting of the top beam of the pipeline bridge at kallupalam was completed on both sides. The casting and pipe laying through the pipeline bridge Ayathil are completed. Pit for railway Push through work 75% completed. Kallupalam pipeline bridge fabrication work completed. Handrail fixing work is in progress at 54LL OHSR at Manichithodu. 1016mm and 914 mm MS pipe Valve fixation(Air valve and scour valve) work in progress. Vertical connection work at 54LL OHSR completed. Gap closing work near Kwa office and temporary restoration of the road using GSB is completed. Anchor block work completed at manichithodu OHSR. Anchor block work started near the Ayathil pipeline bridge. The amount for caution charges for the railway push-through work was received from the Head office on 18.1.2022 and work started on 23.1.2023. The Railway push-through work was completed. Hydro testing completed. 914 mm Interconnection work to booster pump house at Anandhawalleswaram is completed. Scour valve fixed on the 400mm DI line near kwa office was completed. Valve chamber work at WTP and AR camp is completed. Valve fixing work is completed.
.
Kollam Project Dn EE |
Date: 29/03/2023 |
Work in progress | 99% Completed
914 mm gravity main – 5714.38 m laid out of 6130m,1016 mm clear water pumping main - 3716.31m laid out of 3835m. Hydro testing of pipelines - 914 mm- 5341.5m completed, 1016mm - 3562m completed. Valve chamber works- 10 Nos completed 6 Nos balance. Cathodic protection work in progress. The whole plastering work of 54LL OHSR at Manichithodu was completed and the Painting work was completed. The casting of the top beam of the pipeline bridge at kallupalam was completed on both sides. The casting and pipe laying through the pipeline bridge Ayathil are completed. Pit for railway Push through work 75% completed. Kallupalam pipeline bridge fabrication work completed. Handrail fixing work is in progress at 54LL OHSR at Manichithodu. 1016mm and 914 mm MS pipe Valve fixation(Air valve and scour valve) work in progress. Vertical connection work at 54LL OHSR completed. Gap closing work near Kwa office and temporary restoration of the road using GSB is completed. Anchor block work completed at manichithodu OHSR. Anchor block work started near the Ayathil pipeline bridge. The amount for caution charges for the railway push-through work was received from the Head office on 18.1.2022 and work started on 23.1.2023. The Railway push-through work was completed. Hydro testing completed. 914 mm Interconnection work to booster pump house at Anandhawalleswaram is completed. Scour valve fixed on 400mm DI line near kwa office completed. Valve chamber work at WTP and AR camp is completed.Valve fixing work is in progress.
.