Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Supplying, laying, Commissioning and maintaining 1016mm dia.8.8mm thick M.S Clear Water pumping main from TP to OHBR at Manichithode, 914mm M .S CWGM form Manichithode to Anandavalleswaram and Construction of 54LL OHSR at Manichithode

Project Supplying, laying, Commissioning and maintaining 1016mm dia.8.8mm thick M.S Clear Water pumping main from TP to OHBR at Manichithode, 914mm M .S CWGM form Manichithode to Anandavalleswaram and Construction of 54LL OHSR at Manichithode
Project Code KLMGOK0117465P3
Type Package
Main Project PROJECTS UNDER KERALA INFRA.INVT. FUND BOARD KIIFB(74)-Augmentation of WSS to Kollam Corporation Phase II(7503)
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description Supplying, laying, Commissioning and maintaining 1016mm dia.8.8mm thick M.S Clear Water pumping main from TP to OHSR at Manichithode, 914mm M .S CWGM form Manichithode to Anandavalleswaram and Construction of 54LL OHSR at Manichithode - TS Amount 2350000000(235 cr)
Status On-going
District Kollam
Executing Office Kollam Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 476169000
TS Number KWA/CE(SR)/18-2016-17 dtd 23/01/2017
Technical specification Supplying, laying, Commissioning and maintaining 1016mm dia.8.8mm thick M.S Clear Water pumping main - 3835 metre , 914mm M .S CWGM 6130 meter and Construction of 54LL OHSR
Contractor M/S Shree Contractor (Mob: 9829855082)

No project review have been added to this project

Reported Issues

Issue date Solved On Action Taken On Category Description Comments Issue Status
26 Oct 2022 Pending Pending Approval/Permissions Related (from other departments excluding road cut permission and land related) Kallupalam bridge pipe rack for laying 914mm MS pipe Issue solved and pipe rack erected and pipe laying work completed at Kallupalam on 28.12.2022 Action Taken
23 Aug 2022 Pending Pending Approval/Permissions Related (from other departments excluding road cut permission and land related) ഞാങ്കടവ് കുടിവെള്ള പദ്ധതിക്ക് വേണ്ടി പൈപ്പ് ലൈൻ സ്ഥാപിക്കുന്നതിനുവേണ്ടി റോഡ് കട്ട് ചെയ്യുന്നത് സംബന്ധിച്ച് Issue solved Action Taken

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 30/08/2019
Scheduled date of Completion as per agreement 28 Feb 2021
Expected date of Completion 31/03/2023

Processing Dates

TS Date 22 Jan 2018
Estimate Approval 22 Jan 2018
NIT Approval 22 Mar 2018
Tender Closing 17 Dec 2018
Technichal Pre-Qualification 26 Feb 2019
Price bid opening 26 Feb 2019

Approval Dates

Workorder Date 24 Jun 2019
NA 30 Aug 2019

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kollam Project Dn EE
Date: 30/03/2023

Work has been completed | 100% Completed

914 mm gravity main – 5714.38 m laid out of 6130m,1016 mm clear water pumping main - 3716.31m laid out of 3835m. Hydro testing of pipelines - 914 mm- 5341.5m completed, 1016mm - 3562m completed. Valve chamber works- 10 Nos completed 6 Nos balance. Cathodic protection work in progress. The whole plastering work of 54LL OHSR at Manichithodu was completed and the Painting work was completed. The casting of the top beam of the pipeline bridge at kallupalam was completed on both sides. The casting and pipe laying through the pipeline bridge Ayathil are completed. Pit for railway Push through work 75% completed. Kallupalam pipeline bridge fabrication work completed. Handrail fixing work is in progress at 54LL OHSR at Manichithodu. 1016mm and 914 mm MS pipe Valve fixation(Air valve and scour valve) work in progress. Vertical connection work at 54LL OHSR completed. Gap closing work near Kwa office and temporary restoration of the road using GSB is completed. Anchor block work completed at manichithodu OHSR. Anchor block work started near the Ayathil pipeline bridge. The amount for caution charges for the railway push-through work was received from the Head office on 18.1.2022 and work started on 23.1.2023. The Railway push-through work was completed. Hydro testing completed. 914 mm Interconnection work to booster pump house at Anandhawalleswaram is completed. Scour valve fixed on the 400mm DI line near kwa office was completed. Valve chamber work at WTP and AR camp is completed. Valve fixing work is completed. .

Kollam Project Dn EE
Date: 29/03/2023

Work in progress | 99% Completed

914 mm gravity main – 5714.38 m laid out of 6130m,1016 mm clear water pumping main - 3716.31m laid out of 3835m. Hydro testing of pipelines - 914 mm- 5341.5m completed, 1016mm - 3562m completed. Valve chamber works- 10 Nos completed 6 Nos balance. Cathodic protection work in progress. The whole plastering work of 54LL OHSR at Manichithodu was completed and the Painting work was completed. The casting of the top beam of the pipeline bridge at kallupalam was completed on both sides. The casting and pipe laying through the pipeline bridge Ayathil are completed. Pit for railway Push through work 75% completed. Kallupalam pipeline bridge fabrication work completed. Handrail fixing work is in progress at 54LL OHSR at Manichithodu. 1016mm and 914 mm MS pipe Valve fixation(Air valve and scour valve) work in progress. Vertical connection work at 54LL OHSR completed. Gap closing work near Kwa office and temporary restoration of the road using GSB is completed. Anchor block work completed at manichithodu OHSR. Anchor block work started near the Ayathil pipeline bridge. The amount for caution charges for the railway push-through work was received from the Head office on 18.1.2022 and work started on 23.1.2023. The Railway push-through work was completed. Hydro testing completed. 914 mm Interconnection work to booster pump house at Anandhawalleswaram is completed. Scour valve fixed on 400mm DI line near kwa office completed. Valve chamber work at WTP and AR camp is completed.Valve fixing work is in progress. .