Project | Construction of 20LL OHSR at TP site |
---|---|
Project Code | KLMGOK0117465P2 |
Type | Package |
Main Project | PROJECTS UNDER KERALA INFRA.INVT. FUND BOARD KIIFB(74)-Augmentation of WSS to Kollam Corporation Phase II(7503) |
Funding Agency | KIIFB |
Category | KIIFB |
Type of scheme | Water Supply |
Scheme | KIIFB |
Description | Construction of 20LL OHSR at TP site TS amount RS. 68810000 (6.881 Crore) |
Status | On-going |
District | Kollam |
Executing Office | Kollam Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 68810000 |
TS Number | KWA/CE(SR)/18-2016-17 dtd 23/01/2017 |
Technical specification | 20 LL OHSR Stage height 20m |
Contractor | Sivaprasad S (Mob: 9447206962) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 22/03/2019 |
---|---|
Scheduled date of Completion as per agreement | 22 Jan 2020 |
Expected date of Completion | 21/07/2020 |
TS Date | 08 May 2018 |
---|---|
Estimate Approval | 08 May 2018 |
Tender Closing | 20 Sep 2018 |
Price bid opening | 22 Sep 2018 |
Workorder Date | 07 Jan 2019 |
---|---|
NA | 23 Jan 2019 |
Kollam Project HD |
Date: 19/10/2020 |
Work has been completed | 100% Completed
work completed.