Construction of 20LL OHSR at TP site

Project Construction of 20LL OHSR at TP site
Project Code KLMGOK0117465P2
Type Package
Main Project PROJECTS UNDER KERALA INFRA.INVT. FUND BOARD KIIFB(74)-Augmentation of WSS to Kollam Corporation Phase II(7503)
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description Construction of 20LL OHSR at TP site TS amount RS. 68810000 (6.881 Crore)
Status On-going
District Kollam
Executing Office Kollam Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 68810000
TS Number KWA/CE(SR)/18-2016-17 dtd 23/01/2017
Technical specification 20 LL OHSR Stage height 20m
Contractor Sivaprasad S (Mob: 9447206962)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 22/03/2019
Scheduled date of Completion as per agreement 22 Jan 2020
Expected date of Completion 21/07/2020

Processing Dates

TS Date 08 May 2018
Estimate Approval 08 May 2018
Tender Closing 20 Sep 2018
Price bid opening 22 Sep 2018

Approval Dates

Workorder Date 07 Jan 2019
NA 23 Jan 2019

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kollam Project HD
Date: 19/10/2020

Work has been completed | 100% Completed

work completed.

Kollam Project HD
Date: 01/09/2020

Work in progress | 92% Completed

Structure completed. Plastering work progressing.