| Project | Augmentation of Water Supply Scheme to Kollam Corporation - Phase –II-Road restoration under package I KeralapuramVayanasala |
|---|---|
| Project Code | KLMGOK0117465P6 |
| Type | Package |
| Main Project | PROJECTS UNDER KERALA INFRA.INVT. FUND BOARD KIIFB(74)-Augmentation of WSS to Kollam Corporation Phase II(7503) |
| Funding Agency | KIIFB |
| Category | KIIFB |
| Type of scheme | Water Supply |
| Scheme | KIIFB |
| Description | Augmentation of Water Supply Scheme to Kollam Corporation - Phase –II-Road restoration under package I Keralapuram Vayanasala T S Amount RS.11936000.00 (One Crore Nineteen Lakh and Thirty Six Thousand Only ) |
| Status | On-going |
| District | Kollam |
| Executing Office | Kollam Project Dn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 11936000 |
| TS Number | TS/2018-2019/2018/11447 dtd 20.10.2018 |
| Technical specification | Earth work Escavation,Construction of GSB & WMM |
| Contractor | S Raju (Mob: 9447206743) |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 24/01/2019 |
|---|---|
| Scheduled date of Completion as per agreement | 23 Apr 2019 |
| Expected date of Completion | 23/03/2019 |
| TS Date | 20 Oct 2018 |
|---|---|
| Estimate Approval | 20 Oct 2018 |
| NIT Approval | 20 Oct 2018 |
| Tender Closing | 01 Dec 2018 |
| Technichal Pre-Qualification | 01 Dec 2018 |
| Price bid opening | 03 Dec 2018 |
| Workorder Date | 01 Jan 2019 |
|---|---|
| NA | 24 Jan 2019 |
| Kollam Project HD |
| Date: 18/06/2020 |
Work has been completed | 100% Completed