| Project | Augmentation of Water Supply Scheme to Kollam Corporation - Phase –II-Road restoration under package I Kuttichira thattarkonam |
|---|---|
| Project Code | KLMGOK0117465P7 |
| Type | Package |
| Main Project | PROJECTS UNDER KERALA INFRA.INVT. FUND BOARD KIIFB(74)-Augmentation of WSS to Kollam Corporation Phase II(7503) |
| Funding Agency | KIIFB |
| Category | KIIFB |
| Type of scheme | Water Supply |
| Scheme | KIIFB |
| Description | Augmentation of Water Supply Scheme to Kollam Corporation - Phase –II-Road restoration under package I Kuttichira thattarkonam TS Amount RS. 6074000.00 (Rupees Sixty Lakhs and Seventy Four Thousand) |
| Status | On-going |
| District | Kollam |
| Executing Office | Kollam Project Dn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 6074000 |
| TS Number | TS/2018 --2019/2018/11446 dtd 22/10/2018 |
| Technical specification | Earth work Excavation, Construction of GSB,WMM |
| Contractor | S Raju (Mob: 9447206743) |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 20/02/2019 |
|---|---|
| Scheduled date of Completion as per agreement | 19 May 2019 |
| Expected date of Completion | 30/03/2020 |
| TS Date | 22 Oct 2018 |
|---|---|
| Estimate Approval | 22 Oct 2018 |
| NIT Approval | 22 Oct 2021 |
| Tender Closing | 24 Dec 2018 |
| Technichal Pre-Qualification | 24 Dec 2018 |
| Price bid opening | 26 Dec 2018 |
| Workorder Date | 01 Feb 2019 |
|---|---|
| NA | 20 Feb 2019 |
| Kollam Project HD |
| Date: 10/09/2020 |
Work has been completed | 100% Completed
Road restoration work at Thattarukonam - Kuttichira.
| Kollam Project HD |
| Date: 19/06/2020 |
Work in progress | 95% Completed
work in progress.