Project | Augmentation of Water Supply Scheme to Kollam Corporation - Phase –II-Road restoration under package I Kuttichira thattarkonam |
---|---|
Project Code | KLMGOK0117465P7 |
Type | Package |
Main Project | PROJECTS UNDER KERALA INFRA.INVT. FUND BOARD KIIFB(74)-Augmentation of WSS to Kollam Corporation Phase II(7503) |
Funding Agency | KIIFB |
Category | KIIFB |
Type of scheme | Water Supply |
Scheme | KIIFB |
Description | Augmentation of Water Supply Scheme to Kollam Corporation - Phase –II-Road restoration under package I Kuttichira thattarkonam TS Amount RS. 6074000.00 (Rupees Sixty Lakhs and Seventy Four Thousand) |
Status | On-going |
District | Kollam |
Executing Office | Kollam Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 6074000 |
TS Number | TS/2018 --2019/2018/11446 dtd 22/10/2018 |
Technical specification | Earth work Excavation, Construction of GSB,WMM |
Contractor | S Raju (Mob: 9447206743) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 20/02/2019 |
---|---|
Scheduled date of Completion as per agreement | 19 May 2019 |
Expected date of Completion | 30/03/2020 |
TS Date | 22 Oct 2018 |
---|---|
Estimate Approval | 22 Oct 2018 |
NIT Approval | 22 Oct 2021 |
Tender Closing | 24 Dec 2018 |
Technichal Pre-Qualification | 24 Dec 2018 |
Price bid opening | 26 Dec 2018 |
Workorder Date | 01 Feb 2019 |
---|---|
NA | 20 Feb 2019 |
Kollam Project HD |
Date: 10/09/2020 |
Work has been completed | 100% Completed
Road restoration work at Thattarukonam - Kuttichira.
Kollam Project HD |
Date: 19/06/2020 |
Work in progress | 95% Completed
work in progress.