Augmentation of Water Supply Scheme to Kollam Corporation - Phase –II-Road restoration under package I Kuttichira thattarkonam

Project Augmentation of Water Supply Scheme to Kollam Corporation - Phase –II-Road restoration under package I Kuttichira thattarkonam
Project Code KLMGOK0117465P7
Type Package
Main Project PROJECTS UNDER KERALA INFRA.INVT. FUND BOARD KIIFB(74)-Augmentation of WSS to Kollam Corporation Phase II(7503)
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description Augmentation of Water Supply Scheme to Kollam Corporation - Phase –II-Road restoration under package I Kuttichira thattarkonam TS Amount RS. 6074000.00 (Rupees Sixty Lakhs and Seventy Four Thousand)
Status On-going
District Kollam
Executing Office Kollam Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 6074000
TS Number TS/2018 --2019/2018/11446 dtd 22/10/2018
Technical specification Earth work Excavation, Construction of GSB,WMM
Contractor S Raju (Mob: 9447206743)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 20/02/2019
Scheduled date of Completion as per agreement 19 May 2019
Expected date of Completion 30/03/2020

Processing Dates

TS Date 22 Oct 2018
Estimate Approval 22 Oct 2018
NIT Approval 22 Oct 2021
Tender Closing 24 Dec 2018
Technichal Pre-Qualification 24 Dec 2018
Price bid opening 26 Dec 2018

Approval Dates

Workorder Date 01 Feb 2019
NA 20 Feb 2019

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kollam Project HD
Date: 10/09/2020

Work has been completed | 100% Completed

Road restoration work at Thattarukonam - Kuttichira.

Kollam Project HD
Date: 19/06/2020

Work in progress | 95% Completed

work in progress.