| Project | Augmentation of Water Supply Scheme to Kollam Corporation - Phase –II-Road restoration under package I Puthoor Iverkala |
|---|---|
| Project Code | KLMGOK0117465P8 |
| Type | Package |
| Main Project | PROJECTS UNDER KERALA INFRA.INVT. FUND BOARD KIIFB(74)-Augmentation of WSS to Kollam Corporation Phase II(7503) |
| Funding Agency | KIIFB |
| Category | KIIFB |
| Type of scheme | Water Supply |
| Scheme | KIIFB |
| Description | Augmentation of Water Supply Scheme to Kollam Corporation - Phase –II-Road restoration under package I Puthoor Iverkala T S Amount RS. 2669000.00 (Rupees Twenty Six Lakh and Sixty Nine Thousand Only) |
| Status | On-going |
| District | Kollam |
| Executing Office | Kollam Project Dn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 2669000 |
| TS Number | RdDnKLm/2019-2020/KD/2019/2932dtd 17.06.2019 |
| Technical specification | Road restoration under package I Puthoor Iverkala |
| Contractor | Shaji Mathew,Palathra House (Mob: 9645205080) |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 11/10/2019 |
|---|---|
| Scheduled date of Completion as per agreement | 09 Dec 2019 |
| Expected date of Completion | 09/12/2019 |
| TS Date | 17 Jun 2019 |
|---|---|
| Estimate Approval | 17 Jun 2019 |
| NIT Approval | 17 Jun 2019 |
| Tender Closing | 18 Jul 2019 |
| Technichal Pre-Qualification | 20 Jul 2019 |
| Price bid opening | 20 Jul 2019 |
| Workorder Date | 20 Sep 2019 |
|---|---|
| NA | 11 Oct 2019 |
| Kollam Project HD |
| Date: 19/06/2020 |
Work has been completed | 100% Completed
work completed.