Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Supplying, laying, Commissioning and maintaining 1219mm M.S RW Pumping Main from Intake to TP at Vasoorichira

Project Supplying, laying, Commissioning and maintaining 1219mm M.S RW Pumping Main from Intake to TP at Vasoorichira
Project Code KLMGOK0117465P1
Type Package
Main Project PROJECTS UNDER KERALA INFRA.INVT. FUND BOARD KIIFB(74)-Augmentation of WSS to Kollam Corporation Phase II(7503)
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description Supplying, laying, Commissioning and maintaining 1219mm M.S RW Pumping Main from Intake to TP at Vasoorichira AS Amount Rs.2350000000(235Crore)
Status On-going
District Kollam
Executing Office Kollam Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 1455200000
TS Number KWA/CE(SR)/18-2016-17 dtd 23/01/2017
Technical specification Supplying, laying, Commissioning and maintaining 1219mm M.S pipe 12.5mm thick for a length of 16035m and 10mm thick for a length of 12095m for raw water Pumping Main from Intake to TP at Vasoorichira
Contractor M/s. Koya And Company Construction Ltd. (Mob: 9995954789)

No project review have been added to this project

Reported Issues

Issue date Solved On Action Taken On Category Description Comments Issue Status
15 Feb 2022 Pending Pending Road Cut Related Risk As part of this work, an online application was submitted to the Kollam NH Executive Engineer on 23.11.2020 and to MoRTH for permission to install the pipe on the Elampallur-Nathirikkal road. However, the road was tarred on 11.09.2021 without giving permission to install pipes on this road. The work of laying pipes on this road is also pending. The petition has been re-filed in ROW on 11.01.2022 under No. 1022800 for its approval. A joint meeting of PWD, KWA and MoRTH was also held on 20.01.2022 and 21.01.2022 in the Collector's chamber in the presence of Hon'ble MP Sri. NK.Premachandra to resolve this issue. MoRTH officials asked for special permission from MoRTH. KWA has initiated action for that. As per the decision of the committee, a application was submitted for special permission from MoRTH. No comments available. Pending
01 Feb 2022 Pending Pending Road Cut Related Risk As part of this work, an online application was submitted to the Kollam NH Executive Engineer on 23.11.2020 and to MoRTH for permission to install the pipe on the Elampallur-Nathirikkal road. However, the road was tarred on 11.09.2021 without giving permission to install pipes on this road. The work of laying pipes on this road is also pending. The petition has been re-filed in ROW on 11.01.2022 under No. 1022800 for its approval. A joint meeting of PWD, KWA and MoRTH was also held on 20.01.2022 and 21.01.2022 in the Collector's chamber in the presence of Hon'ble MP Sri. NK.Premachandra to resolve this issue. MoRTH officials asked for special permission from MoRTH. KWA has initiated action for that. No comments available. Pending
13 Jan 2022 Pending Pending Road Cut Related Risk As part of this work, an online application was submitted to the Kollam NH Executive Engineer on 23.11.2020 and to MoRTH for permission to install the pipe on the Elampallur-Nathirikkal road. However, the road was tarred on 11.09.2021 without giving permission to install pipes on this road. The work of laying pipes on this road is also pending. The petition has been re-filed in ROW on 11.01.2022 under No. 1022800 for its approval No comments available. Pending
16 Aug 2021 Pending 13 Sep 2021 Road Cut Related Risk An application was submitted on 23.11.2020 to NH Kollam for permission to cut the Elampalloor - Nanthirikkal NH road for a length of 1.052 km. This application is under consideration at MoRTH Office Thiruvananthapuram.But permission to cut the road has not yet been obtained. It has been learned that the road restoration work of the National Highways Department on the Elampallur-Nandirikkal road will be done soon. Permission to cut the road will not be granted once the works are completed. The laying works are almost completed except this NH Road. No comments added. Action Taken
23 Nov 2020 Pending Pending Road Cut Related Risk An application was submitted on 23.11.2020 to NH Kollam for permission to cut the Elampalloor - Nanthirikkal NH road for a length of 1.052 km. This application is under consideration at MoRTH Office Thiruvananthapuram.But permission to cut the road has not yet been obtained. It has been learned that the road restoration work of the National Highways Department on the Elampallur-Nandirikkal road will be done soon. Permission to cut the road will not be granted once the works are completed. The laying works are almost completed except this NH Road. The same issue had been reported to PMG Invest India (https://pmg.dpiit.gov.in) with docket issue number #KL-3180-8033 No comments available. Pending
23 Nov 2020 Pending Pending Approval/Permissions Related (from other departments excluding road cut permission and land related) As part of this work, an online application was submitted to the Kollam NH Executive Engineer on 23.11.2020 and to MoRTH for permission to install the pipe on the Elampallur-Nathirikkal road. However, the road was tarred on 11.09.2021 without giving permission to install pipes on this road. The work of laying pipes on this road is also pending. The petition has been re-filed in ROW on 11.01.2022 under No. 1022800 for its approval. A joint meeting of PWD, KWA and MoRTH was also held on 20.01.2022 and 21.01.2022 in the Collector's chamber in the presence of Hon'ble MP Sri. NK.Premachandra to resolve this issue. MoRTH officials asked for special permission from MoRTH. KWA has initiated action for that. As per the decision of the committee, a application was submitted for special permission from MoRTH. Application for special permission was submitted on 11/03/2022. The same was rejected by MORTH on 30/5/2022. Further action was taken with KIIFB for obtaining sanction. Details submitted to head office on 7/6/2022. No comments available. Pending

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 02/06/2018
Scheduled date of Completion as per agreement 30 Sep 2021
Expected date of Completion 30/06/2023

Processing Dates

TS Date 23 Jan 2017
Estimate Approval 23 Jan 2017
NIT Approval 23 Jan 2017
Tender Closing 25 Jan 2018
Technichal Pre-Qualification 27 Jan 2018
Price bid opening 27 Jan 2018

Approval Dates

Workorder Date 18 May 2018
NA 02 Jun 2018

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kollam Project HD
Date: 07/05/2024

Work in progress | 98% Completed

98% work completed and sanction pending from MORTH for a length of 1052m in NH 183. Again online application submitted in MORTH portal vide application no.20220821/1/1/16271/124813 for road cutting sanction from Elampalloor to Nanthirikkal and the online application with request submitted to NH Division office on 09/11/2022 and no sanction obtained till date. Again application submitted to NH division kollam on 20/9/2023 for laying pipe line through load bearing duct as per the in principle sanction for laying KWA pipeline IN nh roads by laying pipe line through load carrying utility ducts for pipe line size above 300mm and also joint inspection conducted by MoRTH RO on 4/10/2023 with KWA and NH officials. In continuation of inspection , a letter has been forwarded to RO by EE, KWA on 5/10/2023 for getting special sanctions for laying pipe laying by open trenching. After that MoRTH rejected the proposal on 22/11/2023 stating that the pipe laying may be done by utility duct through microtunneling land acquisition to further shift ROW edge etc to avoid cutting of carriageway. Again KWA applied for pipe laying by open trenching with the recommendation PWD secretary to RO, MoRTH on 30/12/2023. Sanction awaiting. MD has directed to proceed with micro tunnelling for laying the pipe line on 07/02/2024.Micro tunnelling proposal submitted to higher officials on 14/02/2024. A consultancy wing M/s Indian Institute of Trenchless Technology made a site inspection on 2.4.2024 for feasibility study of microtunnelling and report submitted by M/s INSDTT on 15/4/2024 and request for engaging consultancy service of M/s INSDTT or any other recognized agencies submitted to higher office on 20/4/2024. .

Kollam Project Dn EE
Date: 04/05/2024

Work in progress | 98% Completed

98% work completed and sanction pending from MORTH for a length of 1052m in NH 183. Again online application submitted in MORTH portal vide application no.20220821/1/1/16271/124813 for road cutting sanction from Elampalloor to Nanthirikkal and the online application with request submitted to NH Division office on 09/11/2022 and no sanction obtained till date. Again application submitted to NH division kollam on 20/9/2023 for laying pipe line through load bearing duct as per the in principle sanction for laying KWA pipeline IN nh roads by laying pipe line through load carrying utility ducts for pipe line size above 300mm and also joint inspection conducted by MoRTH RO on 4/10/2023 with KWA and NH officials. In continuation of inspection , a letter has been forwarded to RO by EE, KWA on 5/10/2023 for getting special sanctions for laying pipe laying by open trenching. After that MoRTH rejected the proposal on 22/11/2023 stating that the pipe laying may be done by utility duct through microtunneling land acquisition to further shift ROW edge etc to avoid cutting of carriageway. Again KWA applied for pipe laying by open trenching with the recommendation PWD secretary to RO, MoRTH on 30/12/2023. Sanction awaiting. MD has directed to proceed with micro tunnelling for laying the pipe line on 07/02/2024.Micro tunnelling proposal submitted to higher officials on 14/02/2024. A consultancy wing M/s Indian Institute of Trenchless Technology made a site inspection on 2.4.2024 for feasibility study of microtunnelling and report submitted by M/s INSDTT on 15/4/2024 and request for engaging consultancy service of M/s INSDTT or any other recognized agencies submitted to higher office on 20/4/2024. .