- Home
- Supplying, laying, Commissioning and mai...
Supplying, laying, Commissioning and maintaining 1219mm M.S RW Pumping Main from Intake to TP at Vasoorichira
Project |
Supplying, laying, Commissioning and maintaining 1219mm M.S RW Pumping Main from Intake to TP at Vasoorichira |
Project Code |
KLMGOK0117465P1 |
Type |
Package |
Main Project |
PROJECTS UNDER KERALA INFRA.INVT. FUND BOARD KIIFB(74)-Augmentation of WSS to Kollam Corporation Phase II(7503)
|
Funding Agency |
KIIFB |
Category |
KIIFB |
Type of scheme |
Water Supply |
Scheme |
KIIFB |
Description |
Supplying, laying, Commissioning and maintaining 1219mm M.S RW Pumping Main from Intake to TP at Vasoorichira
AS Amount Rs.2350000000(235Crore)
|
Status |
On-going |
District |
Kollam |
Executing Office |
Kollam Project Dn |
Agreement Number |
|
Agreement Date |
|
TS Amount (Rs) |
1455200000 |
TS Number |
KWA/CE(SR)/18-2016-17 dtd 23/01/2017 |
Technical specification |
Supplying, laying, Commissioning and maintaining 1219mm M.S pipe 12.5mm thick for a length of 16035m and 10mm thick for a length of 12095m for raw water Pumping Main from Intake to TP at Vasoorichira
|
Contractor |
M/s. Koya And Company Construction Ltd. (Mob: 9995954789) |
No project review have been added to this project
Reported Issues
Issue date |
Solved On |
Action Taken On |
Category |
Description |
Comments |
Issue Status |
15 Feb 2022 |
Pending |
Pending |
Road Cut Related Risk |
As part of this work, an online application was submitted to the Kollam NH Executive Engineer on 23.11.2020 and to MoRTH for permission to install the pipe on the Elampallur-Nathirikkal road. However, the road was tarred on 11.09.2021 without giving permission to install pipes on this road. The work of laying pipes on this road is also pending. The petition has been re-filed in ROW on 11.01.2022 under No. 1022800 for its approval. A joint meeting of PWD, KWA and MoRTH was also held on 20.01.2022 and 21.01.2022 in the Collector's chamber in the presence of Hon'ble MP Sri. NK.Premachandra to resolve this issue. MoRTH officials asked for special permission from MoRTH. KWA has initiated action for that. As per the decision of the committee, a application was submitted for special permission from MoRTH. |
No comments available. |
Pending |
01 Feb 2022 |
Pending |
Pending |
Road Cut Related Risk |
As part of this work, an online application was submitted to the Kollam NH Executive Engineer on 23.11.2020 and to MoRTH for permission to install the pipe on the Elampallur-Nathirikkal road. However, the road was tarred on 11.09.2021 without giving permission to install pipes on this road. The work of laying pipes on this road is also pending. The petition has been re-filed in ROW on 11.01.2022 under No. 1022800 for its approval. A joint meeting of PWD, KWA and MoRTH was also held on 20.01.2022 and 21.01.2022 in the Collector's chamber in the presence of Hon'ble MP Sri. NK.Premachandra to resolve this issue. MoRTH officials asked for special permission from MoRTH. KWA has initiated action for that. |
No comments available. |
Pending |
13 Jan 2022 |
Pending |
Pending |
Road Cut Related Risk |
As part of this work, an online application was submitted to the Kollam NH Executive Engineer on 23.11.2020 and to MoRTH for permission to install the pipe on the Elampallur-Nathirikkal road. However, the road was tarred on 11.09.2021 without giving permission to install pipes on this road. The work of laying pipes on this road is also pending. The petition has been re-filed in ROW on 11.01.2022 under No. 1022800 for its approval |
No comments available. |
Pending |
16 Aug 2021 |
Pending |
13 Sep 2021 |
Road Cut Related Risk |
An application was submitted on 23.11.2020 to NH Kollam for permission to cut the Elampalloor - Nanthirikkal NH road for a length of 1.052 km. This application is under consideration at MoRTH Office Thiruvananthapuram.But permission to cut the road has not yet been obtained. It has been learned that the road restoration work of the National Highways Department on the Elampallur-Nandirikkal road will be done soon. Permission to cut the road will not be granted once the works are completed. The laying works are almost completed except this NH Road. |
No comments added. |
Action Taken |
23 Nov 2020 |
Pending |
Pending |
Road Cut Related Risk |
An application was submitted on 23.11.2020 to NH Kollam for permission to cut the Elampalloor - Nanthirikkal NH road for a length of 1.052 km. This application is under consideration at MoRTH Office Thiruvananthapuram.But permission to cut the road has not yet been obtained. It has been learned that the road restoration work of the National Highways Department on the Elampallur-Nandirikkal road will be done soon. Permission to cut the road will not be granted once the works are completed. The laying works are almost completed except this NH Road.
The same issue had been reported to PMG Invest India (https://pmg.dpiit.gov.in) with docket issue number #KL-3180-8033 |
No comments available. |
Pending |
23 Nov 2020 |
Pending |
Pending |
Approval/Permissions Related (from other departments excluding road cut permission and land related) |
As part of this work, an online application was submitted to the Kollam NH Executive Engineer on 23.11.2020 and to MoRTH for permission to install the pipe on the Elampallur-Nathirikkal road. However, the road was tarred on 11.09.2021 without giving permission to install pipes on this road. The work of laying pipes on this road is also pending. The petition has been re-filed in ROW on 11.01.2022 under No. 1022800 for its approval. A joint meeting of PWD, KWA and MoRTH was also held on 20.01.2022 and 21.01.2022 in the Collector's chamber in the presence of Hon'ble MP Sri. NK.Premachandra to resolve this issue. MoRTH officials asked for special permission from MoRTH. KWA has initiated action for that. As per the decision of the committee, a application was submitted for special permission from MoRTH. Application for special permission was submitted on 11/03/2022. The same was rejected by MORTH on 30/5/2022. Further action was taken with KIIFB for obtaining sanction. Details submitted to head office on 7/6/2022. |
No comments available. |
Pending |
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
Date of start of Package |
02/06/2018 |
Scheduled date of Completion as per agreement |
30 Sep 2021 |
Expected date of Completion |
30/06/2023 |
Processing Dates
TS Date |
23 Jan 2017 |
Estimate Approval |
23 Jan 2017 |
NIT Approval |
23 Jan 2017 |
Tender Closing |
25 Jan 2018 |
Technichal Pre-Qualification |
27 Jan 2018 |
Price bid opening |
27 Jan 2018 |
Approval Dates
Workorder Date |
18 May 2018 |
NA |
02 Jun 2018 |
Other details
Project Schedule |
View |
Project Components |
View |
Project Officers |
View |
Kollam Project HD |
Date: 07/05/2024 |
Work in progress | 98% Completed
98% work completed and sanction pending from MORTH for a length of 1052m in NH 183. Again online application submitted in MORTH portal vide application no.20220821/1/1/16271/124813 for road cutting sanction from Elampalloor to Nanthirikkal and the online application with request submitted to NH Division office on 09/11/2022 and no sanction obtained till date. Again application submitted to NH division kollam on 20/9/2023 for laying pipe line through load bearing duct as per the in principle sanction for laying KWA pipeline IN nh roads by laying pipe line through load carrying utility ducts for pipe line size above 300mm and also joint inspection conducted by MoRTH RO on 4/10/2023 with KWA and NH officials. In continuation of inspection , a letter has been forwarded to RO by EE, KWA on 5/10/2023 for getting special sanctions for laying pipe laying by open trenching. After that MoRTH rejected the proposal on 22/11/2023 stating that the pipe laying may be done by utility duct through microtunneling land acquisition to further shift ROW edge etc to avoid cutting of carriageway. Again KWA applied for pipe laying by open trenching with the recommendation PWD secretary to RO, MoRTH on 30/12/2023. Sanction awaiting. MD has directed to proceed with micro tunnelling for laying the pipe line on 07/02/2024.Micro tunnelling proposal submitted to higher officials on 14/02/2024. A consultancy wing M/s Indian Institute of Trenchless Technology made a site inspection on 2.4.2024 for feasibility study of microtunnelling and report submitted by M/s INSDTT on 15/4/2024 and request for engaging consultancy service of M/s INSDTT or any other recognized agencies submitted to higher office on 20/4/2024.
.
Kollam Project Dn EE |
Date: 04/05/2024 |
Work in progress | 98% Completed
98% work completed and sanction pending from MORTH for a length of 1052m in NH 183. Again online application submitted in MORTH portal vide application no.20220821/1/1/16271/124813 for road cutting sanction from Elampalloor to Nanthirikkal and the online application with request submitted to NH Division office on 09/11/2022 and no sanction obtained till date. Again application submitted to NH division kollam on 20/9/2023 for laying pipe line through load bearing duct as per the in principle sanction for laying KWA pipeline IN nh roads by laying pipe line through load carrying utility ducts for pipe line size above 300mm and also joint inspection conducted by MoRTH RO on 4/10/2023 with KWA and NH officials. In continuation of inspection , a letter has been forwarded to RO by EE, KWA on 5/10/2023 for getting special sanctions for laying pipe laying by open trenching. After that MoRTH rejected the proposal on 22/11/2023 stating that the pipe laying may be done by utility duct through microtunneling land acquisition to further shift ROW edge etc to avoid cutting of carriageway. Again KWA applied for pipe laying by open trenching with the recommendation PWD secretary to RO, MoRTH on 30/12/2023. Sanction awaiting. MD has directed to proceed with micro tunnelling for laying the pipe line on 07/02/2024.Micro tunnelling proposal submitted to higher officials on 14/02/2024. A consultancy wing M/s Indian Institute of Trenchless Technology made a site inspection on 2.4.2024 for feasibility study of microtunnelling and report submitted by M/s INSDTT on 15/4/2024 and request for engaging consultancy service of M/s INSDTT or any other recognized agencies submitted to higher office on 20/4/2024.
.