KIIFB - Augumentation of WSS to Kollam corporation - phase II- Package V - Supply and erection of raw water pump-set, Package VII - Supply and erection of clear water pump set, Package VIII- Automation, solar panel installation and Construction of Transformer building for Raw water, Approach road, Rubble wall for protecting Lake shore and retaining wall at intake well site Njankadavu and Construction of transformer building for clear water pump house at Vasoorichira.

Project KIIFB - Augumentation of WSS to Kollam corporation - phase II- Package V - Supply and erection of raw water pump-set, Package VII - Supply and erection of clear water pump set, Package VIII- Automation, solar panel installation and Construction of Transformer building for Raw water, Approach road, Rubble wall for protecting Lake shore and retaining wall at intake well site Njankadavu and Construction of transformer building for clear water pump house at Vasoorichira.
Project Code KLMKIIFB0117465P10
Type Package
Main Project PROJECTS UNDER KERALA INFRA.INVT. FUND BOARD KIIFB(74)-Augmentation of WSS to Kollam Corporation Phase II(7503)
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description KIIFB - Augumentation of WSS to Kollam corporation - phase II- Package V - Supply and erection of raw water pump-set, Package VII - Supply and erection of clear water pump set, Package VIII- Automation, solar panel installation and Construction of Transformer building for Raw water, Approach road, Rubble wall for protecting Lake shore and retaining wall at intake well site Njankadavu and Construction of transformer building for clear water pump house at Vasoorichira.
Status On-going
District Kollam
Executing Office Kollam Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 458400000
TS Number WRD/KWA-CE(SR)/EST_TS/5569/2023_6_1_1
Technical specification KIFB - Augumentation of WSS to Kollam corporation - phase II- Package V - Supply and erection of raw water pump-set, Package VII - Supply and erection of clear water pump set, Package VIII- Automation, solar panel installation.
Contractor Chicago Constructions International Pvt Ltd (Mob: 9447111906)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 27/12/2021
Scheduled date of Completion as per agreement 31 May 2022
Expected date of Completion 30/06/2023

Processing Dates

TS Date 07 Aug 2023
Estimate Approval 03 Jan 2022
NIT Approval 05 Jan 2022
Tender Closing 22 Jan 2022
Price bid opening 05 Jan 2024

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kollam Project Dn EE
Date: 16/10/2026

Work in progress | 37% Completed

Plastering for celing under progressing. Retaining wall 5th stretch 3rd lift concreting progress.

Attached images

img img img

Kollam Project Dn EE
Date: 15/10/2026

Work in progress | 37% Completed

Wall plastering of transformer building. Retaining wall 4th stretch final lift shuttering. Maintanance bay plinthbeam shuttering progress.

Attached images

img img img img img