Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
12 Dec 2023 | WORK IN PROGRESS. 835 connection tagged.pipe supplied 59.98%.laying = 28.24% completed.Connection=21%completed. | Chalakudy AE 2 | |
11 Dec 2023 | WORK IN PROGRESS. 835 connection tagged.pipe supplied 59.98%.laying = 28.24% completed.Connection=21%completed. | Chalakudy AE 2 | |
08 Dec 2023 | WORK IN PROGRESS. 835 connection tagged.pipe supplied 59.98%.laying = 28.24% completed.Connection=21%completed. | Chalakudy AE 2 | |
07 Dec 2023 | WORK IN PROGRESS. 835 connection tagged.pipe supplied 59.98%.laying = 28.24% completed.Connection=21%completed. | Chalakudy AE 2 | |
06 Dec 2023 | WORK IN PROGRESS. 835 connection tagged.pipe supplied 59.98%.laying = 28.24% completed.Connection=21%completed. | Chalakudy AE 2 | |
05 Dec 2023 | WORK IN PROGRESS. 835 connection tagged.pipe supplied 59.98%.laying = 28.24% completed.Connection=21%completed. | Chalakudy AE 2 | |
01 Dec 2023 | WORK IN PROGRESS. 835 connection tagged.pipe supplied 59.98%.laying = 28.24% completed.Connection=21%completed. | Chalakudy AE 2 | |
28 Nov 2023 | WORK IN PROGRESS. 835 connection tagged.pipe supplied 59.98%.laying = 28.24% completed.Connection=21%completed. | Chalakudy AE 2 | |
27 Nov 2023 | WORK IN PROGRESS. 835 connection tagged.pipe supplied 59.98%.laying = 28.24% completed.Connection=21%completed. | Chalakudy AE 2 | |
24 Nov 2023 | WORK IN PROGRESS. 810 connection tagged.pipe supplied 59.98%.laying = 28.24% completed.Connection=21%completed. | Chalakudy AE 2 |