Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
04 Nov 2023 | WORK IN PROGRESS. 758 connection tagged.pipe supplied 59.98%.laying = 28.24% completed.Connection=16%completed. | Chalakudy AE 2 | |
02 Nov 2023 | WORK IN PROGRESS. 758 connection tagged.pipe supplied 59.98%.laying = 28.24% completed.Connection=16%completed. | Chalakudy AE 2 | |
31 Oct 2023 | WORK IN PROGRESS. 758 connection tagged.pipe supplied 59.98%.laying = 28.24% completed.Connection=16%completed. | Chalakudy AE 2 | |
28 Oct 2023 | WORK IN PROGRESS. 701 connection tagged.pipe supplied 59.98%.laying = 28.24% completed.Connection=16%completed. | Chalakudy AE 2 | |
27 Oct 2023 | WORK IN PROGRESS. 701 connection tagged.pipe supplied 59.98%.laying = 28.24% completed.Connection=16%completed. | Chalakudy AE 2 | |
26 Oct 2023 | WORK IN PROGRESS. 630 connection tagged.pipe supplied 59.98%.laying = 28.24% completed.Connection=16%completed. | Chalakudy AE 2 | |
21 Oct 2023 | WORK IN PROGRESS. 630 connection tagged.pipe supplied 59.98%.laying = 28.24% completed.Connection=16%completed. | Chalakudy AE 2 | |
20 Oct 2023 | WORK IN PROGRESS. 630 connection tagged.pipe supplied 59.98%.laying = 28.24% completed.Connection=16%completed. | Chalakudy AE 2 | |
18 Oct 2023 | WORK IN PROGRESS. 630 connection tagged.pipe supplied 59.98%.laying = 28.24% completed.Connection=16%completed. | Chalakudy AE 2 | |
17 Oct 2023 | WORK IN PROGRESS. 630 connection tagged.pipe supplied 59.98%.laying = 28.24% completed.Connection=16%completed. | Chalakudy AE 2 |