Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
20 Sep 2023 | WORK IN PROGRESS.503 connection tagged.pipe supplied 59.98%.laying = 28.22% completed.Connection=8.06%completed. | Chalakudy AE 2 | |
16 Sep 2023 | WORK IN PROGRESS.405 connection tagged.pipe supplied 59.98%.laying = 28.22% completed.Connection=8.06%completed | Chalakudy AE 2 | |
14 Sep 2023 | WORK IN PROGRESS.405 connection tagged.pipe supplied 59.98%.laying = 28.21% completed.Connection=8.06%completed | Chalakudy AE 2 | |
13 Sep 2023 | WORK IN PROGRESS.405 connection tagged.pipe supplied 59.98%.laying = 28.21% completed.Connection=8.06%completed | Chalakudy AE 2 | |
11 Sep 2023 | WORK IN PROGRESS.405 connection tagged.pipe supplied 59.98%.laying = 28.20% completed.Connection=8.06%completed | Chalakudy AE 2 | |
08 Sep 2023 | WORK IN PROGRESS.405 connection tagged.pipe supplied 59.98%.laying = 28.20% completed.Connection=8.06%completed | Chalakudy AE 2 | |
07 Sep 2023 | WORK IN PROGRESS.405 connection tagged.pipe supplied 59.98%.laying = 28.20% completed.Connection=8.06%completed | Chalakudy AE 2 | |
05 Sep 2023 | WORK IN PROGRESS.405 connection tagged.pipe supplied 59.98%.laying = 28.20% completed.Connection=8.06%completed | Chalakudy AE 2 | |
04 Sep 2023 | WORK IN PROGRESS.405 connection tagged.pipe supplied 59.98%.laying = 28.20% completed.Connection=8.06%completed | Chalakudy AE 2 | |
02 Sep 2023 | WORK IN PROGRESS.405 connection tagged.pipe supplied 59.98%.laying = 28.20% completed.Connection=8.06%completed | Chalakudy AE 2 |