Project | JJM - WSS to Meloor Grama panchayath (Phase ll) |
---|---|
Project Code | TCRJJM022212397 |
Type | Main project |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | JJM - WSS to Meloor Grama panchayath (Phase ll) |
Status | On-going |
District | Thrissur |
Executing Office | Chalakkudy PH Sn II |
AS Amount (Rs) | 229800000 |
AS Number | G.O(Rt)No.134/2022/WRD Dated,Thiruvananthapuram,23-02-2022 |
TS Amount (Rs) | 212900000 |
TS Number | TS/2022-2023/2021/5931 |
Total Bill Submitted (Rs) | 38204022 |
Total Bill Paid (Rs) | 38204022 |
Population Benefitted | 25000 |
Capacity in MLD | 11.00 |
Actual Project Completion Date | Date is not specified |
Coverage | 100% |
Work Plan | Download |
Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
25 Jun 2024 | Work in progress. 1095 connection tagged. pipe supplied 98.93%.laying = 79.12% completed. Connection=29.74%completed. | Chalakudy AE 2 | |
24 Jun 2024 | Work in progress. 1095 connection tagged. pipe supplied 98.93%.laying = 79.12% completed. Connection=29.74%completed. | Chalakudy AE 2 | |
22 Jun 2024 | Work in progress. 1095 connection tagged. pipe supplied 98.93%.laying = 79.12% completed. Connection=29.74%completed. | Chalakudy AE 2 | |
20 Jun 2024 | Work in progress. 1095 connection tagged. pipe supplied 98.93%.laying = 79.12% completed. Connection=29.74%completed. | Chalakudy AE 2 | |
19 Jun 2024 | Work in progress. 1095 connection tagged. pipe supplied 98.93%.laying = 79.12% completed. Connection=29.74%completed. | Chalakudy AE 2 |
Date of start of Project | 10/11/2022 |
---|---|
Scheduled date of Completion of the Project | 09 Nov 2023 |
Expected date of Completion | 31/12/2023 |
AS Date | 23 Feb 2022 |
---|---|
TS Date | 16 Jun 2022 |
Project Officers | View |
---|