23 Dec 2023 | WORK IN PROGRESS. 835 connection tagged.pipe supplied 59.98%.laying = 28.24% completed.Connection=21%completed | Chalakudy AE 2 | |
22 Dec 2023 | WORK IN PROGRESS. 835 connection tagged.pipe supplied 59.98%.laying = 28.24% completed.Connection=21%completed | Chalakudy AE 2 | |
21 Dec 2023 | WORK IN PROGRESS. 835 connection tagged.pipe supplied 59.98%.laying = 28.24% completed.Connection=21%completed | Chalakudy AE 2 | |
20 Dec 2023 | WORK IN PROGRESS. 835 connection tagged.pipe supplied 59.98%.laying = 28.24% completed.Connection=21%completed | Chalakudy AE 2 | |
19 Dec 2023 | WORK IN PROGRESS. 835 connection tagged.pipe supplied 59.98%.laying = 28.24% completed.Connection=21%completed | Chalakudy AE 2 | |
18 Dec 2023 | WORK IN PROGRESS. 835 connection tagged.pipe supplied 59.98%.laying = 28.24% completed.Connection=21%completed | Chalakudy AE 2 | |
16 Dec 2023 | WORK IN PROGRESS. 835 connection tagged.pipe supplied 59.98%.laying = 28.24% completed.Connection=21%completed | Chalakudy AE 2 | |
15 Dec 2023 | WORK IN PROGRESS. 835 connection tagged.pipe supplied 59.98%.laying = 28.24% completed.Connection=21%completed | Chalakudy AE 2 | |
14 Dec 2023 | WORK IN PROGRESS. 835 connection tagged.pipe supplied 59.98%.laying = 28.24% completed.Connection=21%completed | Chalakudy AE 2 | |
13 Dec 2023 | WORK IN PROGRESS. 835 connection tagged.pipe supplied 59.98%.laying = 28.24% completed.Connection=21%completed. | Chalakudy AE 2 |