Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
31 Jan 2024 | WORK IN PROGRESS. 948 connection tagged.pipe supplied 98.93%.laying = 79.12% completed.Connection=29.74%completed. | Chalakudy AE 2 | |
30 Jan 2024 | WORK IN PROGRESS. 948 connection tagged.pipe supplied 98.93%.laying = 79.12% completed.Connection=29.74%completed. | Chalakudy AE 2 | |
29 Jan 2024 | WORK IN PROGRESS. 948 connection tagged.pipe supplied 98.93%.laying = 79.12% completed.Connection=29.74%completed. | Chalakudy AE 2 | |
27 Jan 2024 | WORK IN PROGRESS. 948 connection tagged.pipe supplied 98.93%.laying = 79.12% completed.Connection=29.74%completed. | Chalakudy AE 2 | |
26 Jan 2024 | WORK IN PROGRESS. 948 connection tagged.pipe supplied 98.93%.laying = 79.12% completed.Connection=29.74%completed. | Chalakudy AE 2 | |
25 Jan 2024 | WORK IN PROGRESS. 948 connection tagged.pipe supplied 98.93%.laying = 79.12% completed.Connection=29.74%completed. | Chalakudy AE 2 | |
25 Jan 2024 | WORK IN PROGRESS. 948 connection tagged.pipe supplied 59.98%.laying = 28.24% completed.Connection=21%completed | Chalakudy AE 2 | |
22 Jan 2024 | WORK IN PROGRESS. 948 connection tagged.pipe supplied 59.98%.laying = 28.24% completed.Connection=21%completed | Chalakudy AE 2 | |
20 Jan 2024 | WORK IN PROGRESS. 835 connection tagged.pipe supplied 59.98%.laying = 28.24% completed.Connection=21%completed | Chalakudy AE 2 | |
18 Jan 2024 | WORK IN PROGRESS. 835 connection tagged.pipe supplied 59.98%.laying = 28.24% completed.Connection=21%completed | Chalakudy AE 2 |