Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
28 Nov 2023 | WORK IN PROGRESS. 835 connection tagged.pipe supplied 59.98%.laying = 28.24% completed.Connection=21%completed. | Chalakudy AE 2 | |
27 Nov 2023 | WORK IN PROGRESS. 835 connection tagged.pipe supplied 59.98%.laying = 28.24% completed.Connection=21%completed. | Chalakudy AE 2 | |
24 Nov 2023 | WORK IN PROGRESS. 810 connection tagged.pipe supplied 59.98%.laying = 28.24% completed.Connection=21%completed. | Chalakudy AE 2 | |
22 Nov 2023 | WORK IN PROGRESS. 810 connection tagged.pipe supplied 59.98%.laying = 28.24% completed.Connection=21%completed. | Chalakudy AE 2 | |
21 Nov 2023 | WORK IN PROGRESS. 810 connection tagged.pipe supplied 59.98%.laying = 28.24% completed.Connection=16%completed. | Chalakudy AE 2 | |
18 Nov 2023 | WORK IN PROGRESS. 810 connection tagged.pipe supplied 59.98%.laying = 28.24% completed.Connection=16%completed. | Chalakudy AE 2 | |
16 Nov 2023 | WORK IN PROGRESS. 810 connection tagged.pipe supplied 59.98%.laying = 28.24% completed.Connection=16%completed. | Chalakudy AE 2 | |
15 Nov 2023 | WORK IN PROGRESS. 810 connection tagged.pipe supplied 59.98%.laying = 28.24% completed.Connection=16%completed. | Chalakudy AE 2 | |
10 Nov 2023 | WORK IN PROGRESS. 772connection tagged.pipe supplied 59.98%.laying = 28.24% completed.Connection=16%completed. | Chalakudy AE 2 | |
07 Nov 2023 | WORK IN PROGRESS. 772connection tagged.pipe supplied 59.98%.laying = 28.24% completed.Connection=16%completed. | Chalakudy AE 2 |