Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
18 Feb 2024 | WORK IN PROGRESS. 956 connection tagged. pipe supplied 98.93%.laying = 79.12% completed. Connection=29.74%completed. | Chalakudy AE 2 | |
17 Feb 2024 | WORK IN PROGRESS. 948 connection tagged.pipe supplied 98.93%.laying = 79.12% completed.Connection=29.74%completed. | Chalakudy AE 2 | |
16 Feb 2024 | WORK IN PROGRESS. 948 connection tagged.pipe supplied 98.93%.laying = 79.12% completed.Connection=29.74%completed. | Chalakudy AE 2 | |
15 Feb 2024 | WORK IN PROGRESS. 948 connection tagged.pipe supplied 98.93%.laying = 79.12% completed.Connection=29.74%completed. | Chalakudy AE 2 | |
14 Feb 2024 | WORK IN PROGRESS. 948 connection tagged.pipe supplied 98.93%.laying = 79.12% completed.Connection=29.74%completed. | Chalakudy AE 2 | |
13 Feb 2024 | WORK IN PROGRESS. 948 connection tagged.pipe supplied 98.93%.laying = 79.12% completed.Connection=29.74%completed. | Chalakudy AE 2 | |
12 Feb 2024 | WORK IN PROGRESS. 948 connection tagged.pipe supplied 98.93%.laying = 79.12% completed.Connection=29.74%completed. | Chalakudy AE 2 | |
08 Feb 2024 | WORK IN PROGRESS. 948 connection tagged.pipe supplied 98.93%.laying = 79.12% completed.Connection=29.74%completed. | Chalakudy AE 2 | |
07 Feb 2024 | WORK IN PROGRESS. 948 connection tagged.pipe supplied 98.93%.laying = 79.12% completed.Connection=29.74%completed. | Chalakudy AE 2 | |
01 Feb 2024 | WORK IN PROGRESS. 948 connection tagged.pipe supplied 98.93%.laying = 79.12% completed.Connection=29.74%completed. | Chalakudy AE 2 |