Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
16 Oct 2023 | WORK IN PROGRESS. 630 connection tagged.pipe supplied 59.98%.laying = 28.24% completed.Connection=16%completed. | Chalakudy AE 2 | |
10 Oct 2023 | WORK IN PROGRESS. 630 connection tagged.pipe supplied 59.98%.laying = 28.24% completed.Connection=16%completed. | Chalakudy AE 2 | |
05 Oct 2023 | WORK IN PROGRESS. 630 connection tagged.pipe supplied 59.98%.laying = 28.24% completed.Connection=16%completed. | Chalakudy AE 2 | |
04 Oct 2023 | WORK IN PROGRESS. 630 connection tagged.pipe supplied 59.98%.laying = 28.24% completed.Connection=16%completed. | Chalakudy AE 2 | |
03 Oct 2023 | WORK IN PROGRESS.576 connection tagged.pipe supplied 59.98%.laying = 28.24% completed.Connection=8.06%completed. | Chalakudy AE 2 | |
30 Sep 2023 | WORK IN PROGRESS.576 connection tagged.pipe supplied 59.98%.laying = 28.24% completed.Connection=8.06%completed. | Chalakudy AE 2 | |
29 Sep 2023 | WORK IN PROGRESS.576 connection tagged.pipe supplied 59.98%.laying = 28.24% completed.Connection=8.06%completed. | Chalakudy AE 2 | |
23 Sep 2023 | WORK IN PROGRESS.503 connection tagged.pipe supplied 59.98%.laying = 28.24% completed.Connection=8.06%completed. | Chalakudy AE 2 | |
22 Sep 2023 | WORK IN PROGRESS.503 connection tagged.pipe supplied 59.98%.laying = 28.23% completed.Connection=8.06%completed. | Chalakudy AE 2 | |
21 Sep 2023 | WORK IN PROGRESS.503 connection tagged.pipe supplied 59.98%.laying = 28.23% completed.Connection=8.06%completed. | Chalakudy AE 2 |