| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 27 Mar 2021 | RWPM-24 km pipe laying completed.Pipe laying work stopped due to ban on road cutting till election, as per order No. EL1-267900/21 dated 15.03.2021 from the District Collector | Nattika Project Dn AE 6 | |
| 26 Mar 2021 | RWPM-24 km pipe laying completed.Pipe laying work stopped due to ban on road cutting till election, as per order No. EL1-267900/21 dated 15.03.2021 from the District Collector | Nattika Project Dn AE 6 | |
| 25 Mar 2021 | RWPM-24 km pipe laying completed.Pipe laying work stopped due to ban on road cutting till election, as per order No. EL1-267900/21 dated 15.03.2021 from the District Collector | Nattika Project Dn AE 6 | |
| 25 Mar 2021 | RWPM-24 km pipe laying completed.Pipe laying work stopped due to ban on road cutting till election, as per order No. EL1-267900/21 dated 15.03.2021 from the District Collector | Nattika Project Dn AE 6 | |
| 24 Mar 2021 | RWPM-24 km pipe laying completed.Pipe laying work stopped due to ban on road cutting till election, as per order No. EL1-267900/21 dated 15.03.2021 from the District Collector | Nattika Project Dn AE 6 | |
| 24 Mar 2021 | Intake well cum pump house and 15MLD WTP - Work completed except electric connection | Nattika Project Dn AE 5 | |
| 23 Mar 2021 | RWPM-24 km pipe laying completed.Pipe laying work stopped due to ban on road cutting till election, as per order No. EL1-267900/21 dated 15.03.2021 from the District Collector | Nattika Project Dn AE 6 | |
| 22 Mar 2021 | RWPM-24 km pipe laying completed.Pipe laying work stopped due to ban on road cutting till election, as per order No. EL1-267900/21 dated 15.03.2021 from The District Collector | Nattika Project Dn AE 6 | |
| 22 Mar 2021 | RWPM-24 km pipe laying completed.Pipe laying work stopped due to ban on road cutting till election, as per order No. EL1-267900/21 dated 15.03.2021 from The District Collector | Nattika Project Dn AE 6 | |
| 22 Mar 2021 | Intake well cum pump house and 15MLD WTP - Work completed except electric connection | Nattika Project Dn AE 5 |