Overall Project Status

Status Date Overall Project Status Project Officer Contact
27 Mar 2021 RWPM-24 km pipe laying completed.Pipe laying work stopped due to ban on road cutting till election, as per order No. EL1-267900/21 dated 15.03.2021 from the District Collector Nattika Project Dn AE 6
26 Mar 2021 RWPM-24 km pipe laying completed.Pipe laying work stopped due to ban on road cutting till election, as per order No. EL1-267900/21 dated 15.03.2021 from the District Collector Nattika Project Dn AE 6
25 Mar 2021 RWPM-24 km pipe laying completed.Pipe laying work stopped due to ban on road cutting till election, as per order No. EL1-267900/21 dated 15.03.2021 from the District Collector Nattika Project Dn AE 6
25 Mar 2021 RWPM-24 km pipe laying completed.Pipe laying work stopped due to ban on road cutting till election, as per order No. EL1-267900/21 dated 15.03.2021 from the District Collector Nattika Project Dn AE 6
24 Mar 2021 RWPM-24 km pipe laying completed.Pipe laying work stopped due to ban on road cutting till election, as per order No. EL1-267900/21 dated 15.03.2021 from the District Collector Nattika Project Dn AE 6
24 Mar 2021 Intake well cum pump house and 15MLD WTP - Work completed except electric connection Nattika Project Dn AE 5
23 Mar 2021 RWPM-24 km pipe laying completed.Pipe laying work stopped due to ban on road cutting till election, as per order No. EL1-267900/21 dated 15.03.2021 from the District Collector Nattika Project Dn AE 6
22 Mar 2021 RWPM-24 km pipe laying completed.Pipe laying work stopped due to ban on road cutting till election, as per order No. EL1-267900/21 dated 15.03.2021 from The District Collector Nattika Project Dn AE 6
22 Mar 2021 RWPM-24 km pipe laying completed.Pipe laying work stopped due to ban on road cutting till election, as per order No. EL1-267900/21 dated 15.03.2021 from The District Collector Nattika Project Dn AE 6
22 Mar 2021 Intake well cum pump house and 15MLD WTP - Work completed except electric connection Nattika Project Dn AE 5