Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
10 Feb 2021 Package I&II - Intake well and 15MLD WTP at Kottapadi - Work completed except electric connection. Charging and commissioning not done. Final Bill submitted Nattika Project Dn AE 5
10 Feb 2021 RWPM- 21.59 km pipe laying completed.Pipe laying in progress Nattika Project Dn AE 6
08 Feb 2021 RWPM- 21.59 km pipe laying completed.Pipe laying in progress Nattika Project Dn AE 6
08 Feb 2021 Package I&II - Intake well and 15MLD WTP at Kottapadi - Work completed except electric connection. Charging and commissioning not done. Final Bill submitted Nattika Project Dn AE 5
06 Feb 2021 RWPM-21.41 km pipe laying completed.Pipe laying in progress Nattika Project Dn AE 6
05 Feb 2021 Work completed except electric connection. Charging and commissioning not done. Final Bill submitted Nattika Project Dn AE 5
05 Feb 2021 21.41 km pipe laying completed.Pipe laying in progress Nattika Project Dn AE 6
03 Feb 2021 RWPM-21.41 km pipe laying completed Nattika Project Dn AE 6
03 Feb 2021 Work completed except electric connection. Charging and commissioning not done. Final Bill submitted Nattika Project Dn AE 5
02 Feb 2021 Work completed except electric connection. Charging and commissioning not done. Final Bill submitted Nattika Project Dn AE 5