| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 12 Apr 2021 | RWPM-24 km pipe laying completed. | Nattika Project Dn AE 6 | |
| 12 Apr 2021 | Intake well and 15MLD WTP Kottapadi - Work completed except electric connection | Nattika Project Dn AE 5 | |
| 11 Apr 2021 | RWPM-24 km pipe laying completed. | Nattika Project Dn AE 6 | |
| 10 Apr 2021 | RWPM-24 km pipe laying completed. | Nattika Project Dn AE 6 | |
| 09 Apr 2021 | RWPM-24 km pipe laying completed. | Nattika Project Dn AE 6 | |
| 08 Apr 2021 | RWPM-24 km pipe laying completed. | Nattika Project Dn AE 6 | |
| 07 Apr 2021 | RWPM-24 km pipe laying completed.Pipe laying work stopped due to ban on road cutting till election, as per order No. EL1-267900/21 dated 15.03.2021 from the District Collector | Nattika Project Dn AE 6 | |
| 06 Apr 2021 | RWPM-24 km pipe laying completed.Pipe laying work stopped due to ban on road cutting till election, as per order No. EL1-267900/21 dated 15.03.2021 from the District Collector | Nattika Project Dn AE 6 | |
| 05 Apr 2021 | RWPM-24 km pipe laying completed.Pipe laying work stopped due to ban on road cutting till election, as per order No. EL1-267900/21 dated 15.03.2021 from the District Collector | Nattika Project Dn AE 6 | |
| 04 Apr 2021 | RWPM-24 km pipe laying completed.Pipe laying work stopped due to ban on road cutting till election, as per order No. EL1-267900/21 dated 15.03.2021 from the District Collector | Nattika Project Dn AE 6 |