| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 03 Apr 2021 | RWPM-24 km pipe laying completed.Pipe laying work stopped due to ban on road cutting till election, as per order No. EL1-267900/21 dated 15.03.2021 from the District Collector | Nattika Project Dn AE 6 | |
| 03 Apr 2021 | Intake well cum Pump House and 15MLD WTP - Work completed except electric connection | Nattika Project Dn AE 5 | |
| 02 Apr 2021 | RWPM-24 km pipe laying completed.Pipe laying work stopped due to ban on road cutting till election, as per order No. EL1-267900/21 dated 15.03.2021 from the District Collector | Nattika Project Dn AE 6 | |
| 01 Apr 2021 | RWPM-24 km pipe laying completed.Pipe laying work stopped due to ban on road cutting till election, as per order No. EL1-267900/21 dated 15.03.2021 from the District Collector | Nattika Project Dn AE 6 | |
| 31 Mar 2021 | RWPM-24 km pipe laying completed.Pipe laying work stopped due to ban on road cutting till election, as per order No. EL1-267900/21 dated 15.03.2021 from the District Collector | Nattika Project Dn AE 6 | |
| 31 Mar 2021 | Intake well cum Pump House and 15MLD WTP - Work completed except electric connection | Nattika Project Dn AE 5 | |
| 30 Mar 2021 | RWPM-24 km pipe laying completed.Pipe laying work stopped due to ban on road cutting till election, as per order No. EL1-267900/21 dated 15.03.2021 from the District Collector | Nattika Project Dn AE 6 | |
| 29 Mar 2021 | RWPM-24 km pipe laying completed.Pipe laying work stopped due to ban on road cutting till election, as per order No. EL1-267900/21 dated 15.03.2021 from the District Collector | Nattika Project Dn AE 6 | |
| 29 Mar 2021 | Intake well cum Pump House and 15MLD WTP - Work completed except electric connection | Nattika Project Dn AE 5 | |
| 28 Mar 2021 | RWPM-24 km pipe laying completed.Pipe laying work stopped due to ban on road cutting till election, as per order No. EL1-267900/21 dated 15.03.2021 from the District Collector | Nattika Project Dn AE 6 |