| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 25 Oct 2023 | Work completed. | Nattika Project Dn | |
| 20 Oct 2023 | Package I - Work completed. Package II - RWPM-39Km pipe laying completed.Chirakkal bridge-Steel fabrication, pipe line works and welding works are completed. | Nattika Project Dn | |
| 10 Oct 2023 | Package I - Work completed except electric connection in WTP. Package II - RWPM-39Km pipe laying completed.Chirakkal bridge-Steel fabrication, pipe line works and welding works are completed, valve fixing works are ongoing. | Nattika Project Dn | |
| 27 Sep 2023 | Package I - Work completed except electric connection in WTP. Package II - RWPM-38 Km pipe laying completed out of 39Km.Chirakkal bridge-Steel fabrication and welding works are completed,pipe line works are ongoing. | Nattika Project Dn | |
| 21 Sep 2023 | Package I - Work completed except electric connection in WTP. Package II - RWPM-38 Km pipe laying completed out of 39Km.Chirakkal bridge-Steel fabrication and welding works are completed. | Nattika Project Dn | |
| 05 Sep 2023 | Package I - Work completed except electric connection in WTP. Package II - RWPM-37.8 Km pipe laying completed out of 39Km.Chirakkal bridge-Steel fabrication and welding works are completed. | Nattika Project Dn | |
| 17 Aug 2023 | Package I - Work completed except electric connection in WTP. Package II - RWPM-37.5 Km pipe laying completed out of 39Km.Chirakkal bridge-Piling ,pile cap work ,column and beam works are completed | Nattika Project Dn | |
| 14 Aug 2023 | Package I - Work completed except electric connection in WTP. Package II - RWPM-37.5 Km pipe laying completed out of 39Km.Chirakkal bridge-Piling ,pile cap work ,column works are completed and Beam works are ongoing | Nattika Project Dn | |
| 09 Aug 2023 | Package I - Work completed except electric connection in WTP. Package II - RWPM-37.5 Km pipe laying completed out of 39Km.Chirakkal bridge-Piling ,pile cap work ,column works are completed and Beam works are ongoing | Nattika Project Dn | |
| 14 Jul 2023 | Package I - Work completed except electric connection in WTP. Package II - RWPM-37.5 Km pipe laying completed out of 39Km. | Nattika Project Dn |