| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 21 Apr 2021 | RWPM-24.44 km pipe laying completed .Pipe laying in progress.33.233 km pipe supplied | Nattika Project Dn AE 6 | |
| 20 Apr 2021 | RWPM-24 km pipe laying completed.Pipe laying in progress. | Nattika Project Dn AE 6 | |
| 19 Apr 2021 | RWPM-24 km pipe laying completed.Pipe laying in progress. | Nattika Project Dn AE 6 | |
| 19 Apr 2021 | Intake well and 15MLD WTP Kottapadi - Work completed except electric connection | Nattika Project Dn AE 5 | |
| 18 Apr 2021 | RWPM-24 km pipe laying completed.Pipe laying in progress. | Nattika Project Dn AE 6 | |
| 17 Apr 2021 | RWPM-24 km pipe laying completed.Pipe laying in progress. | Nattika Project Dn AE 6 | |
| 16 Apr 2021 | RWPM-24 km pipe laying completed. | Nattika Project Dn AE 6 | |
| 15 Apr 2021 | Intake well and 15MLD WTP Kottapadi - Work completed except electric connection | Nattika Project Dn AE 5 | |
| 15 Apr 2021 | RWPM-24 km pipe laying completed. | Nattika Project Dn AE 6 | |
| 13 Apr 2021 | RWPM-24 km pipe laying completed. | Nattika Project Dn AE 6 |