| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 20 Feb 2021 | RWPM-22 km pipe laying completed.Pipe laying in progress | Nattika Project Dn AE 6 | |
| 18 Feb 2021 | RWPM-22 km pipe laying completed.Pipe laying in progress | Nattika Project Dn AE 6 | |
| 18 Feb 2021 | Package I&II - Intake well and 15MLD WTP at Kottapadi - Work completed except electric connection. Charging and commissioning not done. Final Bill submitted | Nattika Project Dn AE 5 | |
| 17 Feb 2021 | Package I&II - Intake well and 15MLD WTP at Kottapadi - Work completed except electric connection. Charging and commissioning not done. Final Bill submitted | Nattika Project Dn AE 5 | |
| 17 Feb 2021 | RWPM- 22 km pipe laying completed.Pipe laying in progress | Nattika Project Dn AE 6 | |
| 16 Feb 2021 | Package I&II - Intake well and 15MLD WTP at Kottapadi - Work completed except electric connection. Charging and commissioning not done. Final Bill submitted | Nattika Project Dn AE 5 | |
| 15 Feb 2021 | Package I&II - Intake well and 15MLD WTP at Kottapadi - Work completed except electric connection. Charging and commissioning not done. Final Bill submitted | Nattika Project Dn AE 5 | |
| 13 Feb 2021 | RWPM- 21.59 km pipe laying completed.Pipe laying in progress | Nattika Project Dn AE 6 | |
| 12 Feb 2021 | Package I&II - Intake well and 15MLD WTP at Kottapadi - Work completed except electric connection. Charging and commissioning not done. Final Bill submitted | Nattika Project Dn AE 5 | |
| 11 Feb 2021 | RWPM- 21.59 km pipe laying completed.Pipe laying in progress | Nattika Project Dn AE 6 |