| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 03 May 2021 | RWPM-25 km pipe laying completed.Pipe laying in progress | Nattika Project Dn AE 5 | |
| 03 May 2021 | RWPM-25 km pipe laying completed.Pipe laying in progress | Nattika Project Dn AE 6 | |
| 01 May 2021 | RWPM-25 km pipe laying completed.Pipe laying in progress | Nattika Project Dn AE 6 | |
| 30 Apr 2021 | RWPM-24.9 km pipe laying completed.Pipe laying in progress | Nattika Project Dn AE 6 | |
| 30 Apr 2021 | Intake well and 15MLD WTP Kottapadi - Work completed except electric connection | Nattika Project Dn AE 5 | |
| 28 Apr 2021 | RWPM-24.9 km pipe laying completed.Pipe laying in progress | Nattika Project Dn AE 6 | |
| 28 Apr 2021 | Intake well and 15MLD WTP Kottapadi - Work completed except electric connection | Nattika Project Dn AE 5 | |
| 26 Apr 2021 | Intake well and 15MLD WTP Kottapadi - Work completed except electric connection | Nattika Project Dn AE 5 | |
| 22 Apr 2021 | RWPM-24.44 km pipe laying completed .Pipe laying in progress.33.233 km pipe supplied | Nattika Project Dn AE 6 | |
| 21 Apr 2021 | Intake well and 15MLD WTP Kottapadi - Work completed except electric connection | Nattika Project Dn AE 5 |