| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 13 Mar 2021 | RWPM-23.8 km pipe laying completed.600 /500 mm DI K9 pipe laying in progress | Nattika Project Dn AE 6 | |
| 12 Mar 2021 | Intake well cum pump house and 15MLD WTP - Work completed except electric connection | Nattika Project Dn AE 5 | |
| 12 Mar 2021 | RWPM-23.8 km pipe laying completed.600 /500 mm DI K9 pipe laying in progress | Nattika Project Dn AE 6 | |
| 10 Mar 2021 | Intake well cum pump house and 15MLD WTP - Work completed except electric connection | Nattika Project Dn AE 5 | |
| 10 Mar 2021 | RWPM-23.8 km pipe laying completed.600 /500 mm DI K9 pipe laying in progress | Nattika Project Dn AE 6 | |
| 08 Mar 2021 | RWPM-23.8 km pipe laying completed.Pipe laying in progress | Nattika Project Dn AE 6 | |
| 08 Mar 2021 | Intake well cum pump house and 15MLD WTP - Work completed except electric connection | Nattika Project Dn AE 5 | |
| 07 Mar 2021 | RWPM-23.8 km pipe laying completed.Pipe laying in progress | Nattika Project Dn AE 6 | |
| 05 Mar 2021 | Intake well cum pump house and 15MLD WTP - Work completed except electric connection | Nattika Project Dn AE 5 | |
| 04 Mar 2021 | RWPM - 23 km pipe laying completed.Pipe laying in progress | Nattika Project Dn AE 6 |