| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 16 May 2021 | Intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 26 km pipe laying completed. Pipe laying work delayed due to heavy rain and lockdown | Nattika Project Dn AE 5 | |
| 14 May 2021 | Intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 26 km pipe laying completed. Pipe laying work in progress | Nattika Project Dn AE 5 | |
| 12 May 2021 | Intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 26 km pipe laying completed. Pipe laying work in progress | Nattika Project Dn AE 5 | |
| 10 May 2021 | Intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 25.50 km pipe laying completed. Pipe laying work in progress | Nattika Project Dn AE 5 | |
| 08 May 2021 | Intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 25.50 km pipe laying completed. Pipe laying work in progress | Nattika Project Dn AE 5 | |
| 07 May 2021 | Intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 25.50 km pipe laying completed. Pipe laying work in progress | Nattika Project Dn AE 5 | |
| 05 May 2021 | ntake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 25.50 km pipe laying completed. Pipe laying work in progress | Nattika Project Dn AE 5 | |
| 04 May 2021 | Intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 25.45 km pipe laying completed. Pipe laying work in progress | Nattika Project Dn AE 5 | |
| 03 May 2021 | RWPM-25.45 km pipe laying completed.Pipe laying in progress | Nattika Project Dn AE 6 | |
| 03 May 2021 | Intake well and 15MLD WTP Kottapadi - Work completed except electric connection | Nattika Project Dn AE 5 |