| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 04 Jul 2021 | Intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 26.5 km pipe laying completed. Pipe laying work stopped due to monsoon ban | Nattika Project Dn AE 5 | |
| 02 Jul 2021 | Intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 26.5 km pipe laying completed. Pipe laying work stopped due to monsoon ban | Nattika Project Dn AE 5 | |
| 30 Jun 2021 | Intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 26.5 km pipe laying completed. Pipe laying work delayed due to heavy rain and lockdown | Nattika Project Dn AE 5 | |
| 29 Jun 2021 | Intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 26.5 km pipe laying completed. Pipe laying work delayed due to heavy rain and lockdown | Nattika Project Dn AE 5 | |
| 27 Jun 2021 | Intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 26.5 km pipe laying completed. Pipe laying work delayed due to heavy rain and lockdown | Nattika Project Dn AE 5 | |
| 23 Jun 2021 | Intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 26.5 km pipe laying completed. Pipe laying work delayed due to heavy rain and lockdown | Nattika Project Dn AE 5 | |
| 22 Jun 2021 | Intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 26.5 km pipe laying completed. Pipe laying work delayed due to heavy rain and lockdown | Nattika Project Dn AE 5 | |
| 20 Jun 2021 | Intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 26.5 km pipe laying completed. Pipe laying work delayed due to heavy rain and lockdown | Nattika Project Dn AE 5 | |
| 16 Jun 2021 | Intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 26.5 km pipe laying completed. Pipe laying work delayed due to heavy rain and lockdown | Nattika Project Dn AE 5 | |
| 14 Jun 2021 | Intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 26.5 km pipe laying completed. Pipe laying work delayed due to heavy rain and lockdown | Nattika Project Dn AE 5 |