| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 26 Jul 2021 | Intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 27 km pipe laying completed. Pipe laying work stopped due to monsoon ban | Nattika Project Dn AE 5 | |
| 24 Jul 2021 | Intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 27 km pipe laying completed. Pipe laying work stopped due to monsoon ban | Nattika Project Dn AE 5 | |
| 22 Jul 2021 | Intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 27 km pipe laying completed. Pipe laying work stopped due to monsoon ban | Nattika Project Dn AE 5 | |
| 19 Jul 2021 | Intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 27 km pipe laying completed. Pipe laying work stopped due to monsoon ban | Nattika Project Dn AE 5 | |
| 17 Jul 2021 | Intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 27 km pipe laying completed. Pipe laying work stopped due to monsoon ban | Nattika Project Dn AE 5 | |
| 15 Jul 2021 | Intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 27 km pipe laying completed. Pipe laying work stopped due to monsoon ban | Nattika Project Dn AE 5 | |
| 13 Jul 2021 | Intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 27 km pipe laying completed. Pipe laying work stopped due to monsoon ban | Nattika Project Dn AE 5 | |
| 10 Jul 2021 | Intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 26.5 km pipe laying completed. Pipe laying work stopped due to monsoon ban | Nattika Project Dn AE 5 | |
| 09 Jul 2021 | Intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 26.5 km pipe laying completed. Pipe laying work stopped due to monsoon ban | Nattika Project Dn AE 5 | |
| 06 Jul 2021 | Intake well and 15MLD WTP Kottapadi - Work completed except electric connection. RWPM - 26.5 km pipe laying completed. Pipe laying work stopped due to monsoon ban | Nattika Project Dn AE 5 |