| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 05 Dec 2024 | Package 1- Commisioned at 20/5/2024. Package 2- Commisioned on 24/5/2024 .package 3 – pumping main from manjalapuram to kambipalam and kelakam junction trial run done 4 (part -I) -Manjalampuram pump house trial run done and poovathumchola pump house currently got KSEB connection Package 4 (part II)- Pumping main from Kelakam junction to poovathumchola trial run done, Package 5 -Commissioned on 23/5/2024, Package 5 (part II) - currently got KSEB connection | Koothuparamba Proj AE 2 | |
| 28 Nov 2024 | Package 1- Commisioned at 20/5/2024. Package 2- Commisioned on 24/5/2024 .package 3 – pumping main from manjalapuram to kambipalam and kelakam junction trial run done 4 (part -I) -Manjalampuram pump house trial run done and poovathumchola pump house currently got KSEB connection Package 4 (part II)- Pumping main from Kelakam junction to poovathumchola trial run done, Package 5 -Commissioned on 23/5/2024, Package 5 (part II) - currently got KSEB connection | Koothuparamba Proj AE 2 | |
| 23 Nov 2024 | Package 1- Commisioned at 20/5/2024. Package 2- Commisioned on 24/5/2024 .package 3 – pumping main from manjalapuram to kambipalam and kelakam junction trial run done 4 (part -I) -Manjalampuram pump house trial run done and poovathumchola pump house currently got KSEB connection Package 4 (part II)- Pumping main from Kelakam junction to poovathumchola trial run done, Package 5 -Commissioned on 23/5/2024, Package 5 (part II) - currently got KSEB connection | Koothuparamba Proj AE 2 | |
| 19 Nov 2024 | Package 1- Commisioned at 20/5/2024. Package 2- Commisioned on 24/5/2024 .package 3 – pumping main from manjalapuram to kambipalam and kelakam junction trial run done 4 (part -I) -Manjalampuram pump house trial run done and poovathumchola pump house currently got KSEB connection Package 4 (part II)- Pumping main from Kelakam junction to poovathumchola trial run done, Package 5 -Commissioned on 23/5/2024, Package 5 (part II) - currently got KSEB connection | Koothuparamba Proj AE 2 | |
| 15 Nov 2024 | Package 1- Commisioned at 20/5/2024. Package 2- Commisioned on 24/5/2024 .package 3 – pumping main from manjalapuram to kambipalam and kelakam junction trial run done 4 (part -I) -Manjalampuram pump house trial run done and poovathumchola pump house currently got KSEB connection Package 4 (part II)- Pumping main from Kelakam junction to poovathumchola trial run done, Package 5 -Commissioned on 23/5/2024, Package 5 (part II) - currently got KSEB connection | Koothuparamba Proj AE 2 | |
| 07 Nov 2024 | Package 1- Commisioned at 20/5/2024. Package 2- Commisioned on 24/5/2024 .package 3 – pumping main from manjalapuram to kambipalam and kelakam junction trial run done 4 (part -I) -Manjalampuram pump house trial run done and poovathumchola pump house currently got KSEB connection Package 4 (part II)- Pumping main from Kelakam junction to poovathumchola trial run done, Package 5 -Commissioned on 23/5/2024, Package 5 (part II) - currently got KSEB connection | Koothuparamba Proj AE 2 | |
| 02 Nov 2024 | Package 1- Commisioned at 20/5/2024. Package 2- Commisioned on 24/5/2024 .package 3 – pumping main from manjalapuram to kambipalam and kelakam junction trial run done 4 (part -I) -Manjalampuram pump house trial run done and poovathumchola pump house currently got KSEB connection Package 4 (part II)- Pumping main from Kelakam junction to poovathumchola trial run done, Package 5 -Commissioned on 23/5/2024, Package 5 (part II) - currently got KSEB connection | Koothuparamba Proj AE 2 | |
| 29 Oct 2024 | Package 1- Commisioned at 20/5/2024. Package 2- Commisioned on 24/5/2024 .package 3 – pumping main from manjalapuram to kambipalam and kelakam junction trial run done 4 (part -I) -Manjalampuram pump house trial run done and poovathumchola pump house currently got KSEB connection Package 4 (part II)- Pumping main from Kelakam junction to poovathumchola trial run done, Package 5 -Commissioned on 23/5/2024, Package 5 (part II) - currently got KSEB connection | Koothuparamba Proj AE 2 | |
| 22 Oct 2024 | Package 1- Commisioned at 20/5/2024. Package 2- Commisioned on 24/5/2024 .package 3 – pumping main from manjalapuram to kambipalam and kelakam junction trial run done 4 (part -I) -Manjalampuram pump house trial run done and poovathumchola pump house currently got KSEB connection Package 4 (part II)- Pump house from Kelakam junction to poovathumchola trial run done, Package 5 -Commissioned on 23/5/2024, Package 5 (part II) - currently got KSEB connection | Koothuparamba Proj AE 2 | |
| 18 Oct 2024 | Package 1- Commisioned at 20/5/2024. Package 2- Commisioned on 24/5/2024 .package 3 – Waiting for KSEB Connection 4 (part -I) -Manjalampuram pump house charging on progress. Poovathumchola pump house waiting for KSEB connection , Package 4 (part II)- Waiting for KSEB Connection , Package 5 -Commissioned on 23/5/2024, Package 5 (part II) - waiting for KSEB connection | Koothuparamba Proj AE 2 |