Status Date |
Overall Project Status |
Project Officer |
Contact |
06 Apr 2022 |
Package I - All structural works completed. Plastering , mechanical works progressing..Power line extension and erection of transformer completed. And charged the transformer on 4/3/2. Package II- 165 Km pipe supplied , 155 km of various dia pipes laid, GI, MS work progressing .KNG road pipe line, HDPE pipe work completed. |
Malappuram Project Dn |
|
30 Mar 2022 |
Package I filter, clarifier unit SUMP ,OHSR ,All structural works etc. work completed. Plastering , mechanical works progressing..Power line extension and erection of transformer completed. And charged the transformer on 4/3/2. Package II- 165 Km pipe supplied , 155 km of various dia pipes laid, GI, MS work progressing .KNG road pipe line work progressing,Laying of HDPE completed. Malappuram Malappuram Project Malappuram Proje Malappuram |
Malappuram Project Dn |
|
29 Mar 2022 |
Package I filter, clarifier unit SUMP ,OHSR ,All structural works etc. work completed. Plastering , mechanical works progressing..Power line extension and erection of transformer completed. And charged the transformer on 4/3/2. Package II- 165 Km pipe supplied , 145 km of various dia pipes laid, GI, MS work progressing .KNG road pipe line work progressing,Laying of HDPE completed. Malappuram Malappuram Project Malappuram Proje |
Malappuram Project Dn |
|
28 Mar 2022 |
Package I filter, clarifier unit SUMP ,OHSR ,All structural works etc. work completed. Plastering work progressing..Power line extension and erection of transformer completed. And charged the transformer on 4/3/2. Package II- 165 Km pipe supplied , 145 km of various dia pipes laid, GI, MS work progressing .KNG road pipe line work progressing,Laying of HDPE completed. Malappuram Malappuram Project |
Malappuram Project Dn |
|
26 Mar 2022 |
Package I filter, clarifier unit SUMP ,OHSR ,All structural works etc. work completed. Plastering work progressing..Power line extension and erection of transformer completed. And charged the transformer on 4/3/2. Package II- 165 Km pipe supplied , 145 km of various dia pipes laid, GI, MS work progressing .KNG road pipe line work progressing,Laying of HDPE completed. Malappuram Malappuram Project |
Malappuram Project Dn |
|
24 Mar 2022 |
Package I filter, clarifier unit SUMP ,OHSR ,All structural works etc. work completed. Plastering work progressing..Power line extension and erection of transformer completed. And charged the transformer on 4/3/2. Package II- 165 Km pipe supplied , 145 km of various dia pipes laid, GI, MS work progressing .KNG road pipe line work progressing,Laying of HDPE completed. Malappuram |
Malappuram Project Dn |
|
23 Mar 2022 |
Package I filter, clarifier unit SUMP ,OHSR ,All structural works etc. work completed. Plastering work progressing..Power line extension and erection of transformer completed. And charged the transformer on 4/3/2. Package II- 165 Km pipe supplied , 145 km of various dia pipes laid, GI, MS work progressing .KNG road pipe line work progressing,Laying of HDPE completed. |
Malappuram Project Dn |
|
05 Mar 2022 |
Package I filter, clarifier unit SUMP ,OHSR ,All structural works etc. work completed. Plastering work progressing..Power line extension and erection of transformer completed. And charged the transformer on 4/3/2. Package II- 165 Km pipe supplied , 145 km of various dia pipes laid, GI, MS work progressing .KNG road pipe line work progressing,Laying of HDPE completed. |
Malappuram Project Dn |
|
02 Mar 2022 |
Package I filter, clarifier unit SUMP etc. work completed. Plastering also completed.OHSR floor slab completed side wall completed.Roof slab shuttering progressing.Power line extension and erection of transformer completed. Plastering work of sump inside completed. - OHSR roof slab concrete completed.Package II- 165 Km pipe supplied , 145 km of various dia pipes laid, GI, MS work progressing .KNG road pipe line work progressing,Laying of HDPE completed. Malappuram |
Malappuram Project Dn |
|
25 Feb 2022 |
Package I filter, clarifier unit SUMP etc. work completed. Plastering also completed.OHSR floor slab completed side wall completed.Roof slab shuttering progressing.Power line extension and erection of transformer completed. Plastering work of sump inside completed. OHSR Side wall completed.- OHSR roof slab concrete completed.Package II- 165 Km pipe supplied , 145 km of various dia pipes laid, GI, MS work progressing .KNG road pipe line work progressing,Laying of HDPE completed. |
Malappuram Project Dn |
|