Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
06 Apr 2022 Package I - All structural works completed. Plastering , mechanical works progressing..Power line extension and erection of transformer completed. And charged the transformer on 4/3/2. Package II- 165 Km pipe supplied , 155 km of various dia pipes laid, GI, MS work progressing .KNG road pipe line, HDPE pipe work completed. Malappuram Project Dn
30 Mar 2022 Package I filter, clarifier unit SUMP ,OHSR ,All structural works etc. work completed. Plastering , mechanical works progressing..Power line extension and erection of transformer completed. And charged the transformer on 4/3/2. Package II- 165 Km pipe supplied , 155 km of various dia pipes laid, GI, MS work progressing .KNG road pipe line work progressing,Laying of HDPE completed. Malappuram Malappuram Project Malappuram Proje Malappuram Malappuram Project Dn
29 Mar 2022 Package I filter, clarifier unit SUMP ,OHSR ,All structural works etc. work completed. Plastering , mechanical works progressing..Power line extension and erection of transformer completed. And charged the transformer on 4/3/2. Package II- 165 Km pipe supplied , 145 km of various dia pipes laid, GI, MS work progressing .KNG road pipe line work progressing,Laying of HDPE completed. Malappuram Malappuram Project Malappuram Proje Malappuram Project Dn
28 Mar 2022 Package I filter, clarifier unit SUMP ,OHSR ,All structural works etc. work completed. Plastering work progressing..Power line extension and erection of transformer completed. And charged the transformer on 4/3/2. Package II- 165 Km pipe supplied , 145 km of various dia pipes laid, GI, MS work progressing .KNG road pipe line work progressing,Laying of HDPE completed. Malappuram Malappuram Project Malappuram Project Dn
26 Mar 2022 Package I filter, clarifier unit SUMP ,OHSR ,All structural works etc. work completed. Plastering work progressing..Power line extension and erection of transformer completed. And charged the transformer on 4/3/2. Package II- 165 Km pipe supplied , 145 km of various dia pipes laid, GI, MS work progressing .KNG road pipe line work progressing,Laying of HDPE completed. Malappuram Malappuram Project Malappuram Project Dn
24 Mar 2022 Package I filter, clarifier unit SUMP ,OHSR ,All structural works etc. work completed. Plastering work progressing..Power line extension and erection of transformer completed. And charged the transformer on 4/3/2. Package II- 165 Km pipe supplied , 145 km of various dia pipes laid, GI, MS work progressing .KNG road pipe line work progressing,Laying of HDPE completed. Malappuram Malappuram Project Dn
23 Mar 2022 Package I filter, clarifier unit SUMP ,OHSR ,All structural works etc. work completed. Plastering work progressing..Power line extension and erection of transformer completed. And charged the transformer on 4/3/2. Package II- 165 Km pipe supplied , 145 km of various dia pipes laid, GI, MS work progressing .KNG road pipe line work progressing,Laying of HDPE completed. Malappuram Project Dn
05 Mar 2022 Package I filter, clarifier unit SUMP ,OHSR ,All structural works etc. work completed. Plastering work progressing..Power line extension and erection of transformer completed. And charged the transformer on 4/3/2. Package II- 165 Km pipe supplied , 145 km of various dia pipes laid, GI, MS work progressing .KNG road pipe line work progressing,Laying of HDPE completed. Malappuram Project Dn
02 Mar 2022 Package I filter, clarifier unit SUMP etc. work completed. Plastering also completed.OHSR floor slab completed side wall completed.Roof slab shuttering progressing.Power line extension and erection of transformer completed. Plastering work of sump inside completed. - OHSR roof slab concrete completed.Package II- 165 Km pipe supplied , 145 km of various dia pipes laid, GI, MS work progressing .KNG road pipe line work progressing,Laying of HDPE completed. Malappuram Malappuram Project Dn
25 Feb 2022 Package I filter, clarifier unit SUMP etc. work completed. Plastering also completed.OHSR floor slab completed side wall completed.Roof slab shuttering progressing.Power line extension and erection of transformer completed. Plastering work of sump inside completed. OHSR Side wall completed.- OHSR roof slab concrete completed.Package II- 165 Km pipe supplied , 145 km of various dia pipes laid, GI, MS work progressing .KNG road pipe line work progressing,Laying of HDPE completed. Malappuram Project Dn