| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 11 Jul 2022 | Package I - All structural works ,plastering, white washing, filter media, Walland floor tile work etc. completed. Compound wall , mechanical works , progressing..Power line extension and erection of transformer,Raw water pumset erected and charged the transformer on 4/3/2. Package II- 172Km pipe supplied , 165 km of various dia pipes laid, GI, MS work progressing .KNG road pipe line, HDPE pipe work completed. work de;ayed last few days due to heavy rain. | Malappuram Project Dn | |
| 02 Jul 2022 | All structural works ,plastering completed. , mechanical works progressing..Power line extension and erection of transformer,Raw water pumset erected. And charged the transformer on 4/3/2. Package II- 172Km pipe supplied , 165 km of various dia pipes laid, GI, MS work progressing .KNG road pipe line, HDPE pipe work completed. | Malappuram Project Dn | |
| 27 Jun 2022 | All structural works ,plastering completed. , mechanical works progressing..Power line extension and erection of transformer,Raw water pumset erected. And charged the transformer on 4/3/2. Package II- 172Km pipe supplied , 165 km of various dia pipes laid, GI, MS work progressing .KNG road pipe line, HDPE pipe work completed. | Malappuram Project Dn | |
| 23 Jun 2022 | All structural works ,plastering completed. , mechanical works progressing..Power line extension and erection of transformer,Raw water pumset erected. And charged the transformer on 4/3/2. Package II- 172Km pipe supplied , 165 km of various dia pipes laid, GI, MS work progressing .KNG road pipe line, HDPE pipe work completed. | Malappuram Project Dn | |
| 28 May 2022 | All structural works ,plastering completed. , mechanical works progressing..Power line extension and erection of transformer,Raw water pumset erected. And charged the transformer on 4/3/2. Package II- 165 Km pipe supplied , 155 km of various dia pipes laid, GI, MS work progressing .KNG road pipe line, HDPE pipe work completed. | Malappuram Project Dn | |
| 12 May 2022 | All structural works completed. Plastering , mechanical works progressing..Power line extension and erection of transformer completed. And charged the transformer on 4/3/2. Package II- 165 Km pipe supplied , 155 km of various dia pipes laid, GI, MS work progressing .KNG road pipe line, HDPE pipe work completed. | Malappuram Project Dn | |
| 11 May 2022 | All structural works completed. Plastering , mechanical works progressing..Power line extension and erection of transformer completed. And charged the transformer on 4/3/2. Package II- 165 Km pipe supplied , 155 km of various dia pipes laid, GI, MS work progressing .KNG road pipe line, HDPE pipe work completed. | Malappuram Project Dn | |
| 18 Apr 2022 | Package I - All structural works completed. Plastering , mechanical works progressing..Power line extension and erection of transformer completed. And charged the transformer on 4/3/2. Package II- 165 Km pipe supplied , 155 km of various dia pipes laid, GI, MS work progressing .KNG road pipe line, HDPE pipe work completed. | Malappuram Project Dn | |
| 17 Apr 2022 | Package I - All structural works completed. Plastering , mechanical works progressing..Power line extension and erection of transformer completed. And charged the transformer on 4/3/2. Package II- 165 Km pipe supplied , 155 km of various dia pipes laid, GI, MS work progressing .KNG road pipe line, HDPE pipe work completed. | Malappuram Project Dn | |
| 16 Apr 2022 | Package I - All structural works completed. Plastering , mechanical works progressing..Power line extension and erection of transformer completed. And charged the transformer on 4/3/2. Package II- 165 Km pipe supplied , 155 km of various dia pipes laid, GI, MS work progressing .KNG road pipe line, HDPE pipe work completed. | Malappuram Project Dn |