02 Jul 2022 All structural works ,plastering completed. , mechanical works progressing..Power line extension and erection of transformer,Raw water pumset erected. And charged the transformer on 4/3/2. Package II- 172Km pipe supplied , 165 km of various dia pipes laid, GI, MS work progressing .KNG road pipe line, HDPE pipe work completed. Malappuram Project Dn
27 Jun 2022 All structural works ,plastering completed. , mechanical works progressing..Power line extension and erection of transformer,Raw water pumset erected. And charged the transformer on 4/3/2. Package II- 172Km pipe supplied , 165 km of various dia pipes laid, GI, MS work progressing .KNG road pipe line, HDPE pipe work completed. Malappuram Project Dn
23 Jun 2022 All structural works ,plastering completed. , mechanical works progressing..Power line extension and erection of transformer,Raw water pumset erected. And charged the transformer on 4/3/2. Package II- 172Km pipe supplied , 165 km of various dia pipes laid, GI, MS work progressing .KNG road pipe line, HDPE pipe work completed. Malappuram Project Dn
28 May 2022 All structural works ,plastering completed. , mechanical works progressing..Power line extension and erection of transformer,Raw water pumset erected. And charged the transformer on 4/3/2. Package II- 165 Km pipe supplied , 155 km of various dia pipes laid, GI, MS work progressing .KNG road pipe line, HDPE pipe work completed. Malappuram Project Dn
12 May 2022 All structural works completed. Plastering , mechanical works progressing..Power line extension and erection of transformer completed. And charged the transformer on 4/3/2. Package II- 165 Km pipe supplied , 155 km of various dia pipes laid, GI, MS work progressing .KNG road pipe line, HDPE pipe work completed. Malappuram Project Dn
11 May 2022 All structural works completed. Plastering , mechanical works progressing..Power line extension and erection of transformer completed. And charged the transformer on 4/3/2. Package II- 165 Km pipe supplied , 155 km of various dia pipes laid, GI, MS work progressing .KNG road pipe line, HDPE pipe work completed. Malappuram Project Dn
18 Apr 2022 Package I - All structural works completed. Plastering , mechanical works progressing..Power line extension and erection of transformer completed. And charged the transformer on 4/3/2. Package II- 165 Km pipe supplied , 155 km of various dia pipes laid, GI, MS work progressing .KNG road pipe line, HDPE pipe work completed. Malappuram Project Dn
17 Apr 2022 Package I - All structural works completed. Plastering , mechanical works progressing..Power line extension and erection of transformer completed. And charged the transformer on 4/3/2. Package II- 165 Km pipe supplied , 155 km of various dia pipes laid, GI, MS work progressing .KNG road pipe line, HDPE pipe work completed. Malappuram Project Dn
16 Apr 2022 Package I - All structural works completed. Plastering , mechanical works progressing..Power line extension and erection of transformer completed. And charged the transformer on 4/3/2. Package II- 165 Km pipe supplied , 155 km of various dia pipes laid, GI, MS work progressing .KNG road pipe line, HDPE pipe work completed. Malappuram Project Dn
13 Apr 2022 Package I - All structural works completed. Plastering , mechanical works progressing..Power line extension and erection of transformer completed. And charged the transformer on 4/3/2. Package II- 165 Km pipe supplied , 155 km of various dia pipes laid, GI, MS work progressing .KNG road pipe line, HDPE pipe work completed. Malappuram Malappuram Project Dn