Status Date |
Overall Project Status |
Project Officer |
Contact |
03 Dec 2022 |
1. Package I- All civil , electrical, mechanical works copleted , Laying of Pumping main delayed due to public protest at Aryanthodiak and unexpected heavy rain, Raw water and clear water pumpset completed , compound wall almost complted 2. Package II-Distribution System - 350mm to 200mm DI K 9 pipe, 160mm to 90mm PVC Various class pipes and 150mm to 80mm GI Medium pipes-177.6km - 156 km already completed - Inter connection of GI,MS pipe work progressing - Road restoration work along Edavanna -Thiruvali road GSB -WEtmix work copleted as instructed by the PWD. The Initial level of road restoration work submitted to PWD for approval.- The distribution line along aryanthodika interupted due to public protest and unexpected rain- Laying of distribution along Mylongara - Santhipuram road not started due to public protest. |
Malappuram Project Dn |
|
30 Nov 2022 |
1. Package I- All civil , electrical, mechanical works copleted , Laying of Pumping main delayed due to public protest at Aryanthodiak and unexpected heavy rain, Raw water and clear water pumpset completed , compound wall almost complted 2. Package II-Distribution System - 350mm to 200mm DI K 9 pipe, 160mm to 90mm PVC Various class pipes and 150mm to 80mm GI Medium pipes-177.6km - 156 km already completed - Inter connection of GI,MS pipe work progressing - Road restoration work along Edavanna -Thiruvali road GSB -WEtmix work copleted as instructed by the PWD. The Initial level of road restoration work submitted to PWD for approval.- The distribution line along aryanthodika interupted due to public protest and unexpected rain- Laying of distribution along Mylongara - Santhipuram road not started due to public protest. |
Malappuram Project Dn |
|
22 Nov 2022 |
1. Package I- All civil , electrical, mechanical works copleted , Laying of Pumping main delayed due to public protest at Aryanthodiak and unexpected heavy rain, Raw water and clear water pumpset completed , compound wall almost complted 2. Package II-Distribution System - 350mm to 200mm DI K 9 pipe, 160mm to 90mm PVC Various class pipes and 150mm to 80mm GI Medium pipes-177.6km - 156 km already completed - Inter connection of GI,MS pipe work progressing - Road restoration work along Edavanna -Thiruvali road GSB -WEtmix work copleted as instructed by the PWD. The Initial level of road restoration work submitted to PWD for approval.- The distribution line along aryanthodika interupted due to public protest and unexpected rain- Laying of distribution along Mylongara - Santhipuram road not started due to public protest. |
Malappuram Project Dn |
|
17 Nov 2022 |
1. Package I- All civil , electrical, mechanical works copleted , Laying of Pumping main delayed due to public protest at Aryanthodiak and unexpected heavy rain, Raw water and clear water pumpset completed , compound wall almost complted 2. Package II-Distribution System - 350mm to 200mm DI K 9 pipe, 160mm to 90mm PVC Various class pipes and 150mm to 80mm GI Medium pipes-177.6km - 156 km already completed - Inter connection of GI,MS pipe work progressing - Road restoration work along Edavanna -Thiruvali road GSB -WEtmix work copleted as instructed by the PWD. The Initial level of road restoration work submitted to PWD for approval.- The distribution line along aryanthodika interupted due to public protest and unexpected rain- Laying of distribution along Mylongara - Santhipuram road not started due to public protest. |
Malappuram Project Dn |
|
09 Nov 2022 |
1. Package I- All civil , electrical, mechanical works copleted , Laying of Pumping main delayed due to public protest at Aryanthodiak and unexpected heavy rain, Raw water and clear water pumpset completed , compound wall almost complted 2. Package II-Distribution System - 350mm to 200mm DI K 9 pipe, 160mm to 90mm PVC Various class pipes and 150mm to 80mm GI Medium pipes-177.6km - 156 km already completed - Inter connection of GI,MS pipe work progressing - Road restoration work along Edavanna -Thiruvali road GSB -WEtmix work copleted as instructed by the PWD. The Initial level of road restoration work submitted to PWD for approval.- The distribution line along aryanthodika interupted due to public protest and unexpected rain- Laying of distribution along Mylongara - Santhipuram road not started due to public protest. |
Malappuram Project Dn |
|
03 Nov 2022 |
1. Package I- All civil , electrical, mechanical works copleted , Laying of Pumping main delayed due to public protest at Aryanthodiak and unexpected heavy rain, Raw water and clear water pumpset completed , compound wall almost complted 2. Package II-Distribution System - 350mm to 200mm DI K 9 pipe, 160mm to 90mm PVC Various class pipes and 150mm to 80mm GI Medium pipes-177.6km - 156 km already completed - Inter connection of GI,MS pipe work progressing - Road restoration work along Edavanna -Thiruvali road GSB -WEtmix work copleted as instructed by the PWD. The Initial level of road restoration work submitted to PWD for approval.- The distribution line along aryanthodika interupted due to public protest and unexpected rain- Laying of distribution along Mylongara - Santhipuram road not started due to public protest. |
Malappuram Project Dn |
|
28 Oct 2022 |
All plastering, white washing, filter media, Wall and floor tile work ,mechanical works etc. completed. Compound wall , progressing .Power line extension and erection of transformer,Raw water pumset erected, MS Pumping main work progressing and charged the transformer on 4/3/2. Package II- 172Km pipe supplied , 165 km of various dia pipes laid, GI, MS work progressing .KNG road pipe line, HDPE pipe work completed.Inter connection,valve fixing,GI,MS gap linking work progressing |
Malappuram Project Dn |
|
26 Oct 2022 |
All plastering, white washing, filter media, Wall and floor tile work ,mechanical works etc. completed. Compound wall , progressing .Power line extension and erection of transformer,Raw water pumset erected, MS Pumping main work progressing and charged the transformer on 4/3/2. Package II- 172Km pipe supplied , 165 km of various dia pipes laid, GI, MS work progressing .KNG road pipe line, HDPE pipe work completed.Inter connection,valve fixing,GI,MS gap linking work progressing |
Malappuram Project Dn |
|
15 Oct 2022 |
All plastering, white washing, filter media, Wall and floor tile work ,mechanical works etc. completed. Compound wall , progressing .Power line extension and erection of transformer,Raw water pumset erected, MS Pumping main work progressing and charged the transformer on 4/3/2. Package II- 172Km pipe supplied , 165 km of various dia pipes laid, GI, MS work progressing .KNG road pipe line, HDPE pipe work completed.Inter connection,valve fixing,GI,MS gap linking work progressing |
Malappuram Project Dn |
|
07 Oct 2022 |
All plastering, white washing, filter media, Wall and floor tile work ,mechanical works etc. completed. Compound wall , progressing .Power line extension and erection of transformer,Raw water pumset erected, MS Pumping main work progressing and charged the transformer on 4/3/2. Package II- 172Km pipe supplied , 165 km of various dia pipes laid, GI, MS work progressing .KNG road pipe line, HDPE pipe work completed.Inter connection,valve fixing,GI,MS gap linking work progressing. |
Malappuram Project Dn |
|