Overall Project Status

Status Date Overall Project Status Project Officer Contact
03 Dec 2022 1. Package I- All civil , electrical, mechanical works copleted , Laying of Pumping main delayed due to public protest at Aryanthodiak and unexpected heavy rain, Raw water and clear water pumpset completed , compound wall almost complted 2. Package II-Distribution System - 350mm to 200mm DI K 9 pipe, 160mm to 90mm PVC Various class pipes and 150mm to 80mm GI Medium pipes-177.6km - 156 km already completed - Inter connection of GI,MS pipe work progressing - Road restoration work along Edavanna -Thiruvali road GSB -WEtmix work copleted as instructed by the PWD. The Initial level of road restoration work submitted to PWD for approval.- The distribution line along aryanthodika interupted due to public protest and unexpected rain- Laying of distribution along Mylongara - Santhipuram road not started due to public protest. Malappuram Project Dn
30 Nov 2022 1. Package I- All civil , electrical, mechanical works copleted , Laying of Pumping main delayed due to public protest at Aryanthodiak and unexpected heavy rain, Raw water and clear water pumpset completed , compound wall almost complted 2. Package II-Distribution System - 350mm to 200mm DI K 9 pipe, 160mm to 90mm PVC Various class pipes and 150mm to 80mm GI Medium pipes-177.6km - 156 km already completed - Inter connection of GI,MS pipe work progressing - Road restoration work along Edavanna -Thiruvali road GSB -WEtmix work copleted as instructed by the PWD. The Initial level of road restoration work submitted to PWD for approval.- The distribution line along aryanthodika interupted due to public protest and unexpected rain- Laying of distribution along Mylongara - Santhipuram road not started due to public protest. Malappuram Project Dn
22 Nov 2022 1. Package I- All civil , electrical, mechanical works copleted , Laying of Pumping main delayed due to public protest at Aryanthodiak and unexpected heavy rain, Raw water and clear water pumpset completed , compound wall almost complted 2. Package II-Distribution System - 350mm to 200mm DI K 9 pipe, 160mm to 90mm PVC Various class pipes and 150mm to 80mm GI Medium pipes-177.6km - 156 km already completed - Inter connection of GI,MS pipe work progressing - Road restoration work along Edavanna -Thiruvali road GSB -WEtmix work copleted as instructed by the PWD. The Initial level of road restoration work submitted to PWD for approval.- The distribution line along aryanthodika interupted due to public protest and unexpected rain- Laying of distribution along Mylongara - Santhipuram road not started due to public protest. Malappuram Project Dn
17 Nov 2022 1. Package I- All civil , electrical, mechanical works copleted , Laying of Pumping main delayed due to public protest at Aryanthodiak and unexpected heavy rain, Raw water and clear water pumpset completed , compound wall almost complted 2. Package II-Distribution System - 350mm to 200mm DI K 9 pipe, 160mm to 90mm PVC Various class pipes and 150mm to 80mm GI Medium pipes-177.6km - 156 km already completed - Inter connection of GI,MS pipe work progressing - Road restoration work along Edavanna -Thiruvali road GSB -WEtmix work copleted as instructed by the PWD. The Initial level of road restoration work submitted to PWD for approval.- The distribution line along aryanthodika interupted due to public protest and unexpected rain- Laying of distribution along Mylongara - Santhipuram road not started due to public protest. Malappuram Project Dn
09 Nov 2022 1. Package I- All civil , electrical, mechanical works copleted , Laying of Pumping main delayed due to public protest at Aryanthodiak and unexpected heavy rain, Raw water and clear water pumpset completed , compound wall almost complted 2. Package II-Distribution System - 350mm to 200mm DI K 9 pipe, 160mm to 90mm PVC Various class pipes and 150mm to 80mm GI Medium pipes-177.6km - 156 km already completed - Inter connection of GI,MS pipe work progressing - Road restoration work along Edavanna -Thiruvali road GSB -WEtmix work copleted as instructed by the PWD. The Initial level of road restoration work submitted to PWD for approval.- The distribution line along aryanthodika interupted due to public protest and unexpected rain- Laying of distribution along Mylongara - Santhipuram road not started due to public protest. Malappuram Project Dn
03 Nov 2022 1. Package I- All civil , electrical, mechanical works copleted , Laying of Pumping main delayed due to public protest at Aryanthodiak and unexpected heavy rain, Raw water and clear water pumpset completed , compound wall almost complted 2. Package II-Distribution System - 350mm to 200mm DI K 9 pipe, 160mm to 90mm PVC Various class pipes and 150mm to 80mm GI Medium pipes-177.6km - 156 km already completed - Inter connection of GI,MS pipe work progressing - Road restoration work along Edavanna -Thiruvali road GSB -WEtmix work copleted as instructed by the PWD. The Initial level of road restoration work submitted to PWD for approval.- The distribution line along aryanthodika interupted due to public protest and unexpected rain- Laying of distribution along Mylongara - Santhipuram road not started due to public protest. Malappuram Project Dn
28 Oct 2022 All plastering, white washing, filter media, Wall and floor tile work ,mechanical works etc. completed. Compound wall , progressing .Power line extension and erection of transformer,Raw water pumset erected, MS Pumping main work progressing and charged the transformer on 4/3/2. Package II- 172Km pipe supplied , 165 km of various dia pipes laid, GI, MS work progressing .KNG road pipe line, HDPE pipe work completed.Inter connection,valve fixing,GI,MS gap linking work progressing Malappuram Project Dn
26 Oct 2022 All plastering, white washing, filter media, Wall and floor tile work ,mechanical works etc. completed. Compound wall , progressing .Power line extension and erection of transformer,Raw water pumset erected, MS Pumping main work progressing and charged the transformer on 4/3/2. Package II- 172Km pipe supplied , 165 km of various dia pipes laid, GI, MS work progressing .KNG road pipe line, HDPE pipe work completed.Inter connection,valve fixing,GI,MS gap linking work progressing Malappuram Project Dn
15 Oct 2022 All plastering, white washing, filter media, Wall and floor tile work ,mechanical works etc. completed. Compound wall , progressing .Power line extension and erection of transformer,Raw water pumset erected, MS Pumping main work progressing and charged the transformer on 4/3/2. Package II- 172Km pipe supplied , 165 km of various dia pipes laid, GI, MS work progressing .KNG road pipe line, HDPE pipe work completed.Inter connection,valve fixing,GI,MS gap linking work progressing Malappuram Project Dn
07 Oct 2022 All plastering, white washing, filter media, Wall and floor tile work ,mechanical works etc. completed. Compound wall , progressing .Power line extension and erection of transformer,Raw water pumset erected, MS Pumping main work progressing and charged the transformer on 4/3/2. Package II- 172Km pipe supplied , 165 km of various dia pipes laid, GI, MS work progressing .KNG road pipe line, HDPE pipe work completed.Inter connection,valve fixing,GI,MS gap linking work progressing. Malappuram Project Dn