Overall Project Status

Status Date Overall Project Status Project Officer Contact
02 Mar 2023 P-I-Plastering , white washing , filter media , electrical , mechanical works completed. , compound wall work progressing .Power line extension and erection of transformer completed transformer charged on 4/3/22.Raw water pumpset erected, interconnection completed. Laying of Balance pumping main and distribution line work delayed due to Blasting of rock , chemical method is using for blasting of rock and the pumping main work is in progressing. The source of the scheme is same as WSS to Thiruvali , the power connection has to be enhanced . The application given to KSEB and a demand notice issued to Rs. 941650 /- to be remitted . The fund requested from KIIFB. There is an arrear pending amount of Rs. 2246275/- also to be remitted to KSEB. P-II-Distribution System - 350mm to 200mm DI K 9 pipe, 160mm to 90mm PVC Various class pipes and 150mm to 80mm GI Medium pipes-177.6km - 156 km already completed - Inter connection of GI,MS pipe work progressing - Road restoration work along Edavanna -Thiruvali road Tarring work completed as instructed by the PWD. - The distribution line along aryanthodika rock area work progressing - Laying of distribution along Mylongara - Santhipuram road Completed . BM work along Edavanna town completed - Road restoration along Panippara -cherani started Malappuram Project Dn
27 Feb 2023 PACKAGE - I -Plastering , whitewashing , filter media , electrcal , mechanica lworks completed. , compound wall work progressing .Power line extension and erection of transformer completed transformer charged on 4/3/22.Raw water pumpset erected, interconnection completed. Laying of Balance pumping main and distribution line work delayed due to public protest at Aryanthodika .petition given to Edavanna police station for protection to complete the work.Restarted the work and the pumping main work is in progressing PACKAGE -II- Distribution System - 350mm to 200mm DI K 9 pipe, 160mm to 90mm PVC Various class pipes and 150mm to 80mm GI Medium pipes-177.6km - 156 km already completed - Inter connection of GI,MS pipe work progressing - Road restoration work along Edavanna -Thiruvali road Tarring work completed as instructed by the PWD. - The distribution line along aryanthodika interrupted due to public protest - Laying of distribution along Mylongara - Santhipuram road not started due to public protest.petition given to police for protection to complete the work-work restarted and is in progressing . road work along Edavanna town progressing . Malappuram Project Dn
15 Feb 2023 PACKAGE - I -Plastering , whitewashing , filter media , electrcal , mechanica lworks completed. , compound wall work progressing .Power line extension and erection of transformer completed transformer charged on 4/3/22.Raw water pumpset erected, interconnection completed. Laying of Balance pumping main and distribution line work delayed due to public protest at Aryanthodika .petition given to Edavanna police station for protection to complete the work.Restarted the work and the pumping main work is in progressing PACKAGE -II- Distribution System - 350mm to 200mm DI K 9 pipe, 160mm to 90mm PVC Various class pipes and 150mm to 80mm GI Medium pipes-177.6km - 156 km already completed - Inter connection of GI,MS pipe work progressing - Road restoration work along Edavanna -Thiruvali road Tarring work completed as instructed by the PWD. - The distribution line along aryanthodika interrupted due to public protest - Laying of distribution along Mylongara - Santhipuram road not started due to public protest.petition given to police for protection to complete the work-work restarted and is in progressing . road work along Edavanna town progressing . Malappuram Project Dn
01 Feb 2023 PACKAGE - I -Plastering , whitewashing , filter media , electrcal , mechanica lworks completed. , compound wall work progressing .Power line extension and erection of transformer completed transformer charged on 4/3/22.Raw water pumpset erected, interconnection completed. Laying of Balance pumping main and distribution line work delayed due to public protest at Aryanthodika .petition given to Edavanna police station for protection to complete the work.Restarted the work and the pumping main work is in progressing PACKAGE -II- Distribution System - 350mm to 200mm DI K 9 pipe, 160mm to 90mm PVC Various class pipes and 150mm to 80mm GI Medium pipes-177.6km - 156 km already completed - Inter connection of GI,MS pipe work progressing - Road restoration work along Edavanna -Thiruvali road Tarring work completed as instructed by the PWD. - The distribution line along aryanthodika interrupted due to public protest - Laying of distribution along Mylongara - Santhipuram road not started due to public protest.petition given to police for protection to complete the work-work restarted and is in progressing . road work along Edavanna town progressing . Malappuram Project Dn
23 Jan 2023 PACKAGE - I -Plastering , whitewashing , filter media , electrcal , mechanica lworks completed. , compound wall work progressing .Power line extension and erection of transformer completed transformer charged on 4/3/22.Raw water pumpset erected, interconnection completed. Laying of Balance pumping main and distribution line work delayed due to public protest at Aryanthodika .petition given to Edavanna police station for protection to complete the work.Restarted the work and the pumping main work is in progressing PACKAGE -II- Distribution System - 350mm to 200mm DI K 9 pipe, 160mm to 90mm PVC Various class pipes and 150mm to 80mm GI Medium pipes-177.6km - 156 km already completed - Inter connection of GI,MS pipe work progressing - Road restoration work along Edavanna -Thiruvali road Tarring work completed as instructed by the PWD. - The distribution line along aryanthodika interrupted due to public protest - Laying of distribution along Mylongara - Santhipuram road not started due to public protest.petition given to police for protection to complete the work-work restarted and is in progressing . road work along Edavanna town progressing . Malappuram Project Dn
20 Jan 2023 PACKAGE - I -Plastering , whitewashing , filter media , electrcal , mechanica lworks completed. , compound wall work progressing .Power line extension and erection of transformer completed transformer charged on 4/3/22.Raw water pumpset erected, interconnection completed. Laying of Balance pumping main and distribution line work delayed due to public protest at Aryanthodika .petition given to Edavanna police station for protection to complete the work.Restarted the work and the pumping main work is in progressing PACKAGE -II- Distribution System - 350mm to 200mm DI K 9 pipe, 160mm to 90mm PVC Various class pipes and 150mm to 80mm GI Medium pipes-177.6km - 156 km already completed - Inter connection of GI,MS pipe work progressing - Road restoration work along Edavanna -Thiruvali road Tarring work completed as instructed by the PWD. - The distribution line along aryanthodika interrupted due to public protest - Laying of distribution along Mylongara - Santhipuram road not started due to public protest.petition given to police for protection to complete the work-work restarted and is in progressing . road work along Edavanna town progressing . Malappuram Project Dn
30 Dec 2022 Package I- All civil , electrical, mechanical works copleted , Laying of Pumping main delayed due to public protest at Aryanthodiak and unexpected heavy rain, Raw water and clear water pumpset completed , compound wall almost complted 2. Package II-Distribution System - 350mm to 200mm DI K 9 pipe, 160mm to 90mm PVC Various class pipes and 150mm to 80mm GI Medium pipes-177.6km - 156 km already completed - Inter connection of GI,MS pipe work progressing - Road restoration work along Edavanna -Thiruvali road GSB -WEtmix work copleted as instructed by the PWD. The Initial level of road restoration work submitted to PWD for approval.- The distribution line along aryanthodika interupted due to public protest and unexpected rain- Laying of distribution along Mylongara - Santhipuram road not started due to public protest.petition given to Edavanna police station for protection for proceeding the work on 22/12/2022 ,work restarted on 23/12/2022 and is in progressing, expected to be completed before 15 th of January Malappuram Project Dn
29 Dec 2022 . Package I- All civil , electrical, mechanical works copleted , Laying of Pumping main delayed due to public protest at Aryanthodiak and unexpected heavy rain, Raw water and clear water pumpset completed , compound wall almost complted 2. Package II-Distribution System - 350mm to 200mm DI K 9 pipe, 160mm to 90mm PVC Various class pipes and 150mm to 80mm GI Medium pipes-177.6km - 156 km already completed - Inter connection of GI,MS pipe work progressing - Road restoration work along Edavanna -Thiruvali road GSB -WEtmix work copleted as instructed by the PWD. The Initial level of road restoration work submitted to PWD for approval.- The distribution line along aryanthodika interupted due to public protest and unexpected rain- Laying of distribution along Mylongara - Santhipuram road not started due to public protest.petition given to Edavanna police station for protection for proceeding the work on 22/12/2022 ,work restarted on 23/12/2022 and is in progressing, expected to be completed before 15 th of January Malappuram Project Dn
08 Dec 2022 1. Package I- All civil , electrical, mechanical works copleted , Laying of Pumping main delayed due to public protest at Aryanthodiak and unexpected heavy rain, Raw water and clear water pumpset completed , compound wall almost complted 2. Package II-Distribution System - 350mm to 200mm DI K 9 pipe, 160mm to 90mm PVC Various class pipes and 150mm to 80mm GI Medium pipes-177.6km - 156 km already completed - Inter connection of GI,MS pipe work progressing - Road restoration work along Edavanna -Thiruvali road GSB -WEtmix work copleted as instructed by the PWD. The Initial level of road restoration work submitted to PWD for approval.- The distribution line along aryanthodika interupted due to public protest and unexpected rain- Laying of distribution along Mylongara - Santhipuram road not started due to public protest. Malappuram Project Dn
06 Dec 2022 1. Package I- All civil , electrical, mechanical works copleted , Laying of Pumping main delayed due to public protest at Aryanthodiak and unexpected heavy rain, Raw water and clear water pumpset completed , compound wall almost complted 2. Package II-Distribution System - 350mm to 200mm DI K 9 pipe, 160mm to 90mm PVC Various class pipes and 150mm to 80mm GI Medium pipes-177.6km - 156 km already completed - Inter connection of GI,MS pipe work progressing - Road restoration work along Edavanna -Thiruvali road GSB -WEtmix work copleted as instructed by the PWD. The Initial level of road restoration work submitted to PWD for approval.- The distribution line along aryanthodika interupted due to public protest and unexpected rain- Laying of distribution along Mylongara - Santhipuram road not started due to public protest. Malappuram Project Dn