| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 18 Apr 2023 | Package -I-Plastering , white washing , filter media , electrical , mechanical works completed , compound wall work progressing .Power line extension and erection of transformer completed transformer charged on 4/3/22.Raw water pumpset erected, interconnection completed. Laying of Balance pumping main and distribution line work delayed due to Blasting of rock . The publics residing near by areas protest against the blasting of rock . Hence chemical blasting is possible , it takes more time than blasting and 16 m of blasting of rock has to be completed. . The source of the scheme is same as WSS to Thiruvali , the power connection has to be enhanced . The application given to KSEB and a demand notice issued to Rs. 941650 /- to be remitted . The fund requested from KIIFB , Fund released . KSEB has has submitted the Account details and the demanded amount transferred today. There is a sanction to be obtained from KSEB for fixing the CTPT unit . Expecting sanction to be obtained within two or three days from KSEB. The power connection to WTP has obtained on 10-04-2023. Package -II-Distribution System - 350mm to 200mm DI K 9 pipe, 160mm to 90mm PVC Various class pipes and 150mm to 80mm GI Medium pipes-177.6km - 156 km already completed - Inter connection of GI,MS pipe work progressing - Road restoration work along Edavanna -Thiruvali road Tarring work completed as instructed by the PWD. - The distribution line along aryanthodika rock area ( common for Package I & II ) work progressing - Laying of distribution along Mylongara - Santhipuram road Completed . BM work along Edavanna town completed - Road restoration along Panippara -cherani started. O | Malappuram Project Dn | |
| 11 Apr 2023 | Package -I-Plastering , white washing , filter media , electrical , mechanical works completed , compound wall work progressing .Power line extension and erection of transformer completed transformer charged on 4/3/22.Raw water pumpset erected, interconnection completed. Laying of Balance pumping main and distribution line work delayed due to Blasting of rock . The publics residing near by areas protest against the blasting of rock . Hence chemical blasting is possible , it takes more time than blasting and 16 m of blasting of rock has to be completed. . The source of the scheme is same as WSS to Thiruvali , the power connection has to be enhanced . The application given to KSEB and a demand notice issued to Rs. 941650 /- to be remitted . The fund requested from KIIFB , Fund released . KSEB has has submitted the Account details and the demanded amount transferred today. There is a sanction to be obtained from KSEB for fixing the CTPT unit . Expecting sanction to be obtained within two or three days from KSEB. The power connection to WTP has obtained on 10-04-2023. Package -II-Distribution System - 350mm to 200mm DI K 9 pipe, 160mm to 90mm PVC Various class pipes and 150mm to 80mm GI Medium pipes-177.6km - 156 km already completed - Inter connection of GI,MS pipe work progressing - Road restoration work along Edavanna -Thiruvali road Tarring work completed as instructed by the PWD. - The distribution line along aryanthodika rock area ( common for Package I & II ) work progressing - Laying of distribution along Mylongara - Santhipuram road Completed . BM work along Edavanna town completed - Road restoration along Panippara -cherani started. | Malappuram Project Dn | |
| 10 Apr 2023 | Package -I-Plastering , white washing , filter media , electrical , mechanical works completed , compound wall work progressing .Power line extension and erection of transformer completed transformer charged on 4/3/22.Raw water pumpset erected, interconnection completed. Laying of Balance pumping main and distribution line work delayed due to Blasting of rock . The publics residing near by areas protest against the blasting of rock . Hence chemical blasting is possible , it takes more time than blasting and 16 m of blasting of rock has to be completed. . The source of the scheme is same as WSS to Thiruvali , the power connection has to be enhanced . The application given to KSEB and a demand notice issued to Rs. 941650 /- to be remitted . The fund requested from KIIFB, fund released , the demanded amount to be transferred to tomorrow. KSEB has submitted the Account details . The powwr connection to WTP has obtained . Package -II-Distribution System - 350mm to 200mm DI K 9 pipe, 160mm to 90mm PVC Various class pipes and 150mm to 80mm GI Medium pipes-177.6km - 156 km already completed - Inter connection of GI,MS pipe work progressing - Road restoration work along Edavanna -Thiruvali road Tarring work completed as instructed by the PWD. - The distribution line along aryanthodika rock area ( common for Package I & II ) work progressing - Laying of distribution along Mylongara - Santhipuram road Completed . BM work along Edavanna town completed - Road restoration along Panippara -cherani started. | Malappuram Project Dn | |
| 05 Apr 2023 | Package -I-Plastering , white washing , filter media , electrical , mechanical works completed , compound wall work progressing .Power line extension and erection of transformer completed transformer charged on 4/3/22.Raw water pumpset erected, interconnection completed. Laying of Balance pumping main and distribution line work delayed due to Blasting of rock . The publics residing near by areas protest against the blasting of rock . Hence chemical blasting is possible , it takes more time than blasting and 16 m of blasting of rock has to be completed. . The source of the scheme is same as WSS to Thiruvali , the power connection has to be enhanced . The application given to KSEB and a demand notice issued to Rs. 941650 /- to be remitted . The fund requested from KIIFB. There is an arrear pending amount of Rs. 302057/- also to be remitted to KSEB. Package -II-Distribution System - 350mm to 200mm DI K 9 pipe, 160mm to 90mm PVC Various class pipes and 150mm to 80mm GI Medium pipes-177.6km - 156 km already completed - Inter connection of GI,MS pipe work progressing - Road restoration work along Edavanna -Thiruvali road Tarring work completed as instructed by the PWD. - The distribution line along aryanthodika rock area ( common for Package I & II ) work progressing - Laying of distribution along Mylongara - Santhipuram road Completed . BM work along Edavanna town completed - Road restoration along Panippara -cherani started. | Malappuram Project Dn | |
| 03 Apr 2023 | Package -I-Plastering , white washing , filter media , electrical , mechanical works completed , compound wall work progressing .Power line extension and erection of transformer completed transformer charged on 4/3/22.Raw water pumpset erected, interconnection completed. Laying of Balance pumping main and distribution line work delayed due to Blasting of rock . The publics residing near by areas protest against the blasting of rock . Hence chemical blasting is possible , it takes more time than blasting and 16 m of blasting of rock has to be completed. . The source of the scheme is same as WSS to Thiruvali , the power connection has to be enhanced . The application given to KSEB and a demand notice issued to Rs. 941650 /- to be remitted . The fund requested from KIIFB. There is an arrear pending amount of Rs. 302057/- also to be remitted to KSEB. Package -II-Distribution System - 350mm to 200mm DI K 9 pipe, 160mm to 90mm PVC Various class pipes and 150mm to 80mm GI Medium pipes-177.6km - 156 km already completed - Inter connection of GI,MS pipe work progressing - Road restoration work along Edavanna -Thiruvali road Tarring work completed as instructed by the PWD. - The distribution line along aryanthodika rock area ( common for Package I & II ) work progressing - Laying of distribution along Mylongara - Santhipuram road Completed . BM work along Edavanna town completed - Road restoration along Panippara -cherani started. | Malappuram Project Dn | |
| 01 Apr 2023 | Package -I-Plastering , white washing , filter media , electrical , mechanical works completed , compound wall work progressing .Power line extension and erection of transformer completed transformer charged on 4/3/22.Raw water pumpset erected, interconnection completed. Laying of Balance pumping main and distribution line work delayed due to Blasting of rock . The publics residing near by areas protest against the blasting of rock . Hence chemical blasting is possible , it takes more time than blasting and 16 m of blasting of rock has to be completed. . The source of the scheme is same as WSS to Thiruvali , the power connection has to be enhanced . The application given to KSEB and a demand notice issued to Rs. 941650 /- to be remitted . The fund requested from KIIFB. There is an arrear pending amount of Rs. 302057/- also to be remitted to KSEB. Package -II-Distribution System - 350mm to 200mm DI K 9 pipe, 160mm to 90mm PVC Various class pipes and 150mm to 80mm GI Medium pipes-177.6km - 156 km already completed - Inter connection of GI,MS pipe work progressing - Road restoration work along Edavanna -Thiruvali road Tarring work completed as instructed by the PWD. - The distribution line along aryanthodika rock area ( common for Package I & II ) work progressing - Laying of distribution along Mylongara - Santhipuram road Completed . BM work along Edavanna town completed - Road restoration along Panippara -cherani started. | Malappuram Project Dn | |
| 31 Mar 2023 | Package -I-Plastering , white washing , filter media , electrical , mechanical works completed , compound wall work progressing .Power line extension and erection of transformer completed transformer charged on 4/3/22.Raw water pumpset erected, interconnection completed. Laying of Balance pumping main and distribution line work delayed due to Blasting of rock . The publics residing near by areas protest against the blasting of rock . Hence chemical blasting is possible , it takes more time than blasting and 16 m of blasting of rock has to be completed. . The source of the scheme is same as WSS to Thiruvali , the power connection has to be enhanced . The application given to KSEB and a demand notice issued to Rs. 941650 /- to be remitted . The fund requested from KIIFB. There is an arrear pending amount of Rs. 302057/- also to be remitted to KSEB. Package -II-Distribution System - 350mm to 200mm DI K 9 pipe, 160mm to 90mm PVC Various class pipes and 150mm to 80mm GI Medium pipes-177.6km - 156 km already completed - Inter connection of GI,MS pipe work progressing - Road restoration work along Edavanna -Thiruvali road Tarring work completed as instructed by the PWD. - The distribution line along aryanthodika rock area ( common for Package I & II ) work progressing - Laying of distribution along Mylongara - Santhipuram road Completed . BM work along Edavanna town completed - Road restoration along Panippara -cherani starte. | Malappuram Project Dn | |
| 30 Mar 2023 | P-I-Plastering , white washing , filter media , electrical , mechanical works completed. , compound wall work progressing .Power line extension and erection of transformer completed transformer charged on 4/3/22.Raw water pumpset erected, interconnection completed. Laying of Balance pumping main and distribution line work delayed due to Blasting of rock , chemical method is using for blasting of rock and the pumping main work is in progressing. The source of the scheme is same as WSS to Thiruvali , the power connection has to be enhanced . The application given to KSEB and a demand notice issued to Rs. 941650 /- to be remitted . The fund requested from KIIFB. There is an arrear pending amount of Rs. 302057/- also to be remitted to KSEB. P-II-Distribution System - 350mm to 200mm DI K 9 pipe, 160mm to 90mm PVC Various class pipes and 150mm to 80mm GI Medium pipes-177.6km - 156 km already completed - Inter connection of GI,MS pipe work progressing - Road restoration work along Edavanna -Thiruvali road Tarring work completed as instructed by the PWD. - The distribution line along aryanthodika rock area work progressing - Laying of distribution along Mylongara - Santhipuram road Completed . BM work along Edavanna town completed - Road restoration along Panippara -cherani starte. | Malappuram Project Dn | |
| 28 Mar 2023 | P-I-Plastering , white washing , filter media , electrical , mechanical works completed. , compound wall work progressing .Power line extension and erection of transformer completed transformer charged on 4/3/22.Raw water pumpset erected, interconnection completed. Laying of Balance pumping main and distribution line work delayed due to Blasting of rock , chemical method is using for blasting of rock and the pumping main work is in progressing. The source of the scheme is same as WSS to Thiruvali , the power connection has to be enhanced . The application given to KSEB and a demand notice issued to Rs. 941650 /- to be remitted . The fund requested from KIIFB. There is an arrear pending amount of Rs. 2246275/- also to be remitted to KSEB. P-II-Distribution System - 350mm to 200mm DI K 9 pipe, 160mm to 90mm PVC Various class pipes and 150mm to 80mm GI Medium pipes-177.6km - 156 km already completed - Inter connection of GI,MS pipe work progressing - Road restoration work along Edavanna -Thiruvali road Tarring work completed as instructed by the PWD. - The distribution line along aryanthodika rock area work progressing - Laying of distribution along Mylongara - Santhipuram road Completed . BM work along Edavanna town completed - Road restoration along Panippara -cherani starte. | Malappuram Project Dn | |
| 27 Mar 2023 | P-I-Plastering , white washing , filter media , electrical , mechanical works completed. , compound wall work progressing .Power line extension and erection of transformer completed transformer charged on 4/3/22.Raw water pumpset erected, interconnection completed. Laying of Balance pumping main and distribution line work delayed due to Blasting of rock , chemical method is using for blasting of rock and the pumping main work is in progressing. The source of the scheme is same as WSS to Thiruvali , the power connection has to be enhanced . The application given to KSEB and a demand notice issued to Rs. 941650 /- to be remitted . The fund requested from KIIFB. There is an arrear pending amount of Rs. 2246275/- also to be remitted to KSEB. P-II-Distribution System - 350mm to 200mm DI K 9 pipe, 160mm to 90mm PVC Various class pipes and 150mm to 80mm GI Medium pipes-177.6km - 156 km already completed - Inter connection of GI,MS pipe work progressing - Road restoration work along Edavanna -Thiruvali road Tarring work completed as instructed by the PWD. - The distribution line along aryanthodika rock area work progressing - Laying of distribution along Mylongara - Santhipuram road Completed . BM work along Edavanna town completed - Road restoration along Panippara -cherani started | Malappuram Project Dn |