Status Date |
Overall Project Status |
Project Officer |
Contact |
15 Jun 2023 |
UT OF 3067 FHTC, 1477 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6984.5/9000m ,200 mm DI-558/583m, 250mm DI-2188.5/2529m,350mm DI-1460/1894m,300 mm DI -601.5/623m,400 mm DI-362.5/626 ,50 mm pvc-10292/13000 pipe laying work is ongoing. 8th & part bill submitted |
Mathilakam AE |
|
13 Jun 2023 |
OUT OF 3067 FHTC, 1477 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6984.5/9000m ,200 mm DI-558/583m, 250mm DI-2188.5/2529m,350mm DI-1460/1894m,300 mm DI -601.5/623m,400 mm DI-362.5/626 ,50 mm pvc-10292/13000 pipe laying work is ongoing |
Mathilakam AE |
|
06 Jun 2023 |
OUT OF 3067 FHTC, 2280 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6984.5/9000m ,200 mm DI-558/583m, 250mm DI-2188.5/2529m,350mm DI-1460/1894m,300 mm DI -601.5/623m,400 mm DI-362.5/626 ,50 mm pvc-10292/13000 pipe laying work is ongoing |
Mathilakam AE |
|
01 Jun 2023 |
OUT OF 3067 FHTC, 1292 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6984.5/9000m ,200 mm DI-558/583m, 250mm DI-2188.5/2529m,350mm DI-1460/1894m,300 mm DI -601.5/623m,400 mm DI-362.5/626 ,50 mm pvc-10292/13000 pipe laying work is ongoing |
Mathilakam AE |
|
29 May 2023 |
OUT OF 3067 FHTC, 1211 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6984.5/9000m ,200 mm DI-558/583m, 250mm DI-2188.5/2529m,350mm DI-1460/1894m,300 mm DI -601.5/623m,400 mm DI-362.5/626 ,50 mm pvc-10252/13000 pipe laying work is ongoing |
Mathilakam AE |
|
25 May 2023 |
OUT OF 3067 FHTC, 1193 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6984.5/9000m ,200 mm DI-558/583m, 250mm DI-2188.5/2529m,350mm DI-1460/1894m,300 mm DI -601.5/623m,400 mm DI-362.5/626 ,50 mm pvc-10252/13000 pipe laying work is ongoing |
Mathilakam AE |
|
22 May 2023 |
OUT OF 3067 FHTC, 1101 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6984.5/9000m ,200 mm DI-558/583m, 250mm DI-2188.5/2529m,350mm DI-1460/1894m,300 mm DI -601.5/623m,400 mm DI-362.5/626 ,50 mm pvc-10252/13000 pipe laying work is ongoing |
Mathilakam AE |
|
18 May 2023 |
OUT OF 3067 FHTC, 1023 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6984.5/9000m ,200 mm DI-558/583m, 250mm DI-2188.5/2529m,350mm DI-1460/1894m,300 mm DI -601.5/623m,400 mm DI-362.5/626 ,50 mm pvc-10252/13000 pipe laying work is ongoing |
Mathilakam AE |
|
16 May 2023 |
OUT OF 3067 FHTC, 886 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6984.5/9000m ,200 mm DI-558/583m, 250mm DI-2188.5/2529m,350mm DI-1460/1894m,300 mm DI -601.5/623m,400 mm DI-362.5/626 ,50 mm pvc-10252/13000 pipe laying work is ongoing |
Mathilakam AE |
|
11 May 2023 |
OUT OF 3067 FHTC, 886 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6984.5/9000m ,200 mm DI-558/583m, 250mm DI-2188.5/2529m,350mm DI-1460/1894m,300 mm DI -601.5/623m,400 mm DI-362.5/626 ,50 mm pvc-10252/13000 pipe laying work is ongoing |
Mathilakam AE |
|