26 Jun 2024 OUT OF 3067 FHTC, 1920 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-7650.97/9000m ,200 mm DI-558.5/623m, 250mm DI-2272.07/2529m,350mm DI-1672.1/1894m,300 mm DI -621/623m,400 mm DI-566.7/626 ,50 mm pvc-12183.50/13000,500mm DI - 26/159,pipe laying work is ongoing. 13th & part bill submitted. interconnection work and connection ongoing Mathilakam AE
20 Jun 2024 OUT OF 3067 FHTC, 1920 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-7650.97/9000m ,200 mm DI-558.5/623m, 250mm DI-2272.07/2529m,350mm DI-1672.1/1894m,300 mm DI -621/623m,400 mm DI-566.7/626 ,50 mm pvc-12183.50/13000,500mm DI - 26/159,pipe laying work is ongoing. 13th & part bill submitted. interconnection work and connection ongoing Mathilakam AE
18 Jun 2024 OUT OF 3067 FHTC, 1920 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-7650.97/9000m ,200 mm DI-558.5/623m, 250mm DI-2272.07/2529m,350mm DI-1672.1/1894m,300 mm DI -621/623m,400 mm DI-566.7/626 ,50 mm pvc-12183.50/13000,500mm DI - 26/159,pipe laying work is ongoing. 13th & part bill submitted. interconnection work and connection ongoing Mathilakam AE
11 Jun 2024 OUT OF 3067 FHTC, 1920 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-7650.97/9000m ,200 mm DI-558.5/623m, 250mm DI-2272.07/2529m,350mm DI-1672.1/1894m,300 mm DI -621/623m,400 mm DI-566.7/626 ,50 mm pvc-12183.50/13000,500mm DI - 26/159,pipe laying work is ongoing. 13th & part bill submitted. interconnection work and connection ongoing Mathilakam AE
05 Jun 2024 OUT OF 3067 FHTC, 1920 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-7650.97/9000m ,200 mm DI-558.5/623m, 250mm DI-2272.07/2529m,350mm DI-1672.1/1894m,300 mm DI -621/623m,400 mm DI-566.7/626 ,50 mm pvc-12183.50/13000,500mm DI - 26/159,pipe laying work is ongoing. 13th & part bill submitted. interconnection work and connection ongoing Mathilakam AE
21 May 2024 OUT OF 3067 FHTC, 1860 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-7650.97/9000m ,200 mm DI-558.5/623m, 250mm DI-2272.07/2529m,350mm DI-1672.1/1894m,300 mm DI -621/623m,400 mm DI-566.7/626 ,50 mm pvc-12183.50/13000,500mm DI - 26/159,pipe laying work is ongoing. 13th & part bill submitted. interconnection work ongoing Mathilakam AE
17 May 2024 OUT OF 3067 FHTC, 1860 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-7650.97/9000m ,200 mm DI-558.5/623m, 250mm DI-2272.07/2529m,350mm DI-1672.1/1894m,300 mm DI -621/623m,400 mm DI-566.7/626 ,50 mm pvc-12183.50/13000,500mm DI - 26/159,pipe laying work is ongoing. 13th & part bill submitted. interconnection work ongoing Mathilakam AE
13 May 2024 OUT OF 3067 FHTC, 1860 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-7650.97/9000m ,200 mm DI-558.5/623m, 250mm DI-2272.07/2529m,350mm DI-1672.1/1894m,300 mm DI -621/623m,400 mm DI-566.7/626 ,50 mm pvc-12183.50/13000,500mm DI - 26/159,pipe laying work is ongoing. 13th & part bill submitted. Mathilakam AE
06 May 2024 OUT OF 3067 FHTC, 1860 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-7650.97/9000m ,200 mm DI-558.5/623m, 250mm DI-2272.07/2529m,350mm DI-1672.1/1894m,300 mm DI -621/623m,400 mm DI-566.7/626 ,50 mm pvc-12183.50/13000,500mm DI - 26/159,pipe laying work is ongoing. 13th & part bill submitted. Mathilakam AE
23 Apr 2024 OUT OF 3067 FHTC, 1860 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-7650.97/9000m ,200 mm DI-558.5/623m, 250mm DI-2272.07/2529m,350mm DI-1672.1/1894m,300 mm DI -621/623m,400 mm DI-566.7/626 ,50 mm pvc-12183.50/13000,500mm DI - 26/159,pipe laying work is ongoing. 13th & part bill submitted. Mathilakam AE