Status Date |
Overall Project Status |
Project Officer |
Contact |
29 Sep 2023 |
OUT OF 3067 FHTC, 1818 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6984.5/9000m ,200 mm DI-558/583m, 250mm DI-2188.5/2529m,350mm DI-1460/1894m,300 mm DI -601.5/623m,400 mm DI-362.5/626 ,50 mm pvc-12183.50/13000 pipe laying work is ongoing. 11th & part bill submitted |
Mathilakam AE |
|
25 Sep 2023 |
OUT OF 3067 FHTC, 1818 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6984.5/9000m ,200 mm DI-558/583m, 250mm DI-2188.5/2529m,350mm DI-1460/1894m,300 mm DI -601.5/623m,400 mm DI-362.5/626 ,50 mm pvc-12183.50/13000 pipe laying work is ongoing. 11th & part bill submitted |
Mathilakam AE |
|
19 Sep 2023 |
OUT OF 3067 FHTC, 1818 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6984.5/9000m ,200 mm DI-558/583m, 250mm DI-2188.5/2529m,350mm DI-1460/1894m,300 mm DI -601.5/623m,400 mm DI-362.5/626 ,50 mm pvc-12183.50/13000 pipe laying work is ongoing. 11th & part bill submitted |
Mathilakam AE |
|
16 Sep 2023 |
OUT OF 3067 FHTC, 1818 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6984.5/9000m ,200 mm DI-558/583m, 250mm DI-2188.5/2529m,350mm DI-1460/1894m,300 mm DI -601.5/623m,400 mm DI-362.5/626 ,50 mm pvc-12183.50/13000 pipe laying work is ongoing. 11th & part bill submitted |
Mathilakam AE |
|
14 Sep 2023 |
OUT OF 3067 FHTC, 1818 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6984.5/9000m ,200 mm DI-558/583m, 250mm DI-2188.5/2529m,350mm DI-1460/1894m,300 mm DI -601.5/623m,400 mm DI-362.5/626 ,50 mm pvc-12183.50/13000 pipe laying work is ongoing. 11th & part bill submitted |
Mathilakam AE |
|
11 Sep 2023 |
OUT OF 3067 FHTC, 1818 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6984.5/9000m ,200 mm DI-558/583m, 250mm DI-2188.5/2529m,350mm DI-1460/1894m,300 mm DI -601.5/623m,400 mm DI-362.5/626 ,50 mm pvc-12183.50/13000 pipe laying work is ongoing. 11th & part bill submitted |
Mathilakam AE |
|
07 Sep 2023 |
OUT OF 3067 FHTC, 1818 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6984.5/9000m ,200 mm DI-558/583m, 250mm DI-2188.5/2529m,350mm DI-1460/1894m,300 mm DI -601.5/623m,400 mm DI-362.5/626 ,50 mm pvc-12183.50/13000 pipe laying work is ongoing. 11th & part bill submitted |
Mathilakam AE |
|
04 Sep 2023 |
OUT OF 3067 FHTC, 1805 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6984.5/9000m ,200 mm DI-558/583m, 250mm DI-2188.5/2529m,350mm DI-1460/1894m,300 mm DI -601.5/623m,400 mm DI-362.5/626 ,50 mm pvc-12183.50/13000 pipe laying work is ongoing. 11th & part bill submitted |
Mathilakam AE |
|
01 Sep 2023 |
OUT OF 3067 FHTC, 1805 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6984.5/9000m ,200 mm DI-558/583m, 250mm DI-2188.5/2529m,350mm DI-1460/1894m,300 mm DI -601.5/623m,400 mm DI-362.5/626 ,50 mm pvc-12183.50/13000 pipe laying work is ongoing. 11th & part bill submitted |
Mathilakam AE |
|
24 Aug 2023 |
OUT OF 3067 FHTC, 1805 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6984.5/9000m ,200 mm DI-558/583m, 250mm DI-2188.5/2529m,350mm DI-1460/1894m,300 mm DI -601.5/623m,400 mm DI-362.5/626 ,50 mm pvc-12183.50/13000 pipe laying work is ongoing. 11th & part bill submitted |
Mathilakam AE |
|