Status Date |
Overall Project Status |
Project Officer |
Contact |
04 Apr 2023 |
OUT OF 3067 FHTC, 843 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6884.5/9000m ,200 mm DI-558/583m, 250mm DI-2188.5/2529m,350mm DI-1460/1894m,300 mm DI -601.5/623m,400 mm DI-362.5/626 pipe laying work is ongoing |
Mathilakam AE |
|
30 Mar 2023 |
OUT OF 3067 FHTC, 843 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6846.5/9000m ,200 mm DI-558/583m, 250mm DI-2188.5/2529m,350mm DI-1460/1894m,300 mm DI -601.5/623m,400 mm DI-324.5/626 pipe laying work is ongoing |
Mathilakam AE |
|
27 Mar 2023 |
OUT OF 3067 FHTC, 842 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6830/9000m ,200 mm DI-558/583m, 250mm DI-2188.5/2529m,350mm DI-1460/1894m,300 mm DI -601.5/623m,400 mm DI-308/626 pipe laying work is ongoing |
Mathilakam AE |
|
23 Mar 2023 |
OUT OF 3067 FHTC, 835 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6654/9000m ,200 mm DI-558/583m, 250mm DI-2188.5/2529m,350mm DI-1460/1894m,300 mm DI -601.5/623m pipe laying work is ongoing |
Mathilakam AE |
|
21 Mar 2023 |
OUT OF 3067 FHTC, 835 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6599/9000m ,200 mm DI-558/583m, 250mm DI-2188.5/2529m,350mm DI-1460/1894m,300 mm DI -601.5/623m pipe laying work is ongoing |
Mathilakam AE |
|
16 Mar 2023 |
OUT OF 3067 FHTC, 771 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6522/9000m ,200 mm DI-558/583m, 250mm DI-2029/2529m,350mm DI-1427/1894m,300 mm DI -601.5/623m pipe laying work is ongoing |
Mathilakam AE |
|
14 Mar 2023 |
OUT OF 3067 FHTC, 771 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6481.5/9000m ,200 mm DI-558/583m, 250mm DI-2029/2529m,350mm DI-1427/1894m,300 mm DI -601.5/623m pipe laying work is ongoing |
Mathilakam AE |
|
13 Mar 2023 |
OUT OF 3067 FHTC, 771 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6338.5/9000m ,200 mm DI-558/583m, 250mm DI-1886/2529m,350mm DI-1427/1894m,300 mm DI -601.5/623m pipe laying work is ongoing |
Mathilakam AE |
|
09 Mar 2023 |
OUT OF 3067 FHTC, 771 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6338.5/9000m ,200 mm DI-558/583m, 250mm DI-1886/2529m,350mm DI-1427/1894m,300 mm DI -601.5/623m pipe laying work is ongoing |
Mathilakam AE |
|
07 Mar 2023 |
OUT OF 3067 FHTC, 771 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6072/9000m ,200 mm DI-558/583m, 250mm DI-1886/2529m,350mm DI-1410/1894m,300 mm DI -601.5/623m pipe laying work is ongoing |
Mathilakam AE |
|