Status Date |
Overall Project Status |
Project Officer |
Contact |
20 Jan 2023 |
OUT OF 3067 FHTC, 688 FHTC COMPLETED ,HDPE pipe laying is ongoing 90mm-4361.5m ,200 mm DI-492m,250mm DI-1439.5m,350mm DI-428.5m,300 mm DI -275m pipe laying work is ongoing |
Mathilakam AE |
|
19 Jan 2023 |
OUT OF 3067 FHTC, 688 FHTC COMPLETED ,HDPE pipe laying is ongoing 90mm-4332m ,200 mm DI-464.5m,250mm DI-1437.5m,350mm DI-428.5m,300 mm DI -275m pipe laying work is ongoing |
Mathilakam AE |
|
17 Jan 2023 |
OUT OF 3067 FHTC, 688 FHTC COMPLETED ,HDPE pipe laying is ongoing 90mm-4161.5m ,200 mm DI-464.5m,250mm DI-1404m,350mm DI-428.5m,300 mm DI -137.5m pipe laying work is ongoing |
Mathilakam AE |
|
16 Jan 2023 |
OUT OF 3067 FHTC, 688 FHTC COMPLETED ,HDPE pipe laying is ongoing 90mm-4079m ,200 mm DI-464.5m,250mm DI-1404m,350mm DI-428.5m pipe laying work is ongoing |
Mathilakam AE |
|
13 Jan 2023 |
OUT OF 3067 FHTC, 688 FHTC COMPLETED ,HDPE pipe laying is ongoing 90mm-3938m ,200 mm DI-464.5m,250mm DI-1318.5m,350mm DI-428.5m pipe laying work is ongoing |
Mathilakam AE |
|
11 Jan 2023 |
OUT OF 3067 FHTC, 688 FHTC COMPLETED ,HDPE pipe laying is ongoing 90mm-3872m ,200 mm DI-464.5m,250mm DI-1252.5m,350mm DI-428.5m pipe laying work is ongoing
|
Mathilakam AE |
|
10 Jan 2023 |
OUT OF 3067 FHTC, 653 FHTC COMPLETED ,HDPE pipe laying is ongoing 90mm-3817m ,200 mm DI-464.5m,250mm DI-1197.5m,350mm DI-428.5m pipe laying work is ongoing |
Mathilakam AE |
|
07 Jan 2023 |
OUT OF 3067 FHTC, 653 FHTC COMPLETED ,HDPE pipe laying is ongoing 90mm-3773.6m ,200 mm DI-464.5m,250mm DI-1153.5m,350mm DI-428.5m pipe laying work is ongoing |
Mathilakam AE |
|
04 Jan 2023 |
OUT OF 3067 FHTC, 653 FHTC COMPLETED ,HDPE pipe laying is ongoing 90mm-3773.6m ,200 mm DI-464.5m,250mm DI-1153.5m,350mm DI-428.5m pipe laying work is ongoing |
Mathilakam AE |
|
30 Dec 2022 |
OUT OF 3067 FHTC, 653 FHTC COMPLETED ,HDPE pipe laying is ongoing 90mm-3773.6m ,200 mm DI-464.5m,250mm DI-1153.5m,350mm DI-428.5m pipe laying work is ongoing . |
Mathilakam AE |
|